GNSS vs Traditional Survey Set-Out for Blast-Hole Drilling

Blast hole GPS guidance uses high-accuracy GNSS and digital drill designs to guide a drill rig directly to planned hole locations, reducing reliance on physical survey set-out while keeping survey control and verification at the centre of the drilling workflow.

Blast-hole drilling has traditionally relied on a familiar process.

The drill pattern is designed.

Surveyors establish the hole locations in the field.

Those positions are marked using pegs, stakes, paint or other physical set-out.

The drill operator then locates those marks and positions the rig over each hole.

That process works.

But it also creates a repeated physical handover between engineering, survey and production.

Blast hole GPS guidance changes that handover.

Instead of transferring every planned hole from the digital design to a physical peg, the drill rig can receive the drill pattern digitally and navigate directly toward the designed coordinates using RTK GNSS machine guidance.

For large drilling programs, this can significantly change the workflow.

What Is Traditional Blast-Hole Survey Set-Out?

Traditional survey set-out takes the coordinates from the drill design and physically establishes them on the ground.

The workflow may look like:

Drill Design

↓

Survey Data

↓

Surveyor Sets Out Hole

↓

Physical Mark Created

↓

Drill Operator Finds Mark

↓

Machine Positioned

↓

Hole Drilled

For each hole, the digital design is converted into something visible in the field.

This physical mark becomes the operator’s reference.

What Is Blast Hole GPS Guidance?

Blast hole GPS guidance takes a different approach.

The digital drill design is loaded into the machine-guidance system.

The drill rig uses high-accuracy GNSS positioning to determine where it is relative to the planned hole locations.

The operator can then see the target position on the in-cab display and navigate directly toward it.

The workflow becomes:

Drill Design

↓

Digital Drill File

↓

GNSS Machine Guidance

↓

Operator Navigates to Hole

↓

Position Verified

↓

Hole Drilled

The major difference is that the design can remain digital from the office through to the machine.

Does Blast Hole GPS Guidance Replace Surveyors?

No.

This distinction is important.

Machine guidance can reduce the need for repetitive physical hole set-out, but survey remains essential.

Survey is still required for activities such as:

  • Establishing project control
  • Coordinate systems
  • Base station setup
  • Site localisation
  • Design verification
  • Independent machine checks
  • Quality assurance
  • Investigating discrepancies

A better way to describe the change is:

Blast hole GPS guidance can shift survey effort from physically marking every hole toward controlling and verifying the positioning system used by the machine.

Why Traditional Set-Out Works

Physical set-out has several advantages.

It is:

  • Familiar
  • Easy for operators to understand
  • Independent of in-cab machine guidance
  • Visually obvious when the mark remains intact
  • Well established across mining operations

It can also provide a useful physical check during drilling.

The issue is not that traditional survey set-out is ineffective.

The issue is how much effort is required when the number of holes becomes very large.

The Scale Problem

Consider a relatively small drill pattern containing 100 holes.

Each position needs to be established.

Now consider 500 holes.

Then 1,000.

Then repeated drill patterns across an ongoing operation.

The physical set-out workload grows with the drilling program.

The survey team may need to repeatedly:

  1. Access the drill area.
  2. Locate each design coordinate.
  3. Mark the hole.
  4. Move to the next point.
  5. Return if marks are damaged.
  6. Re-establish holes where required.

This is where blast hole GPS guidance becomes particularly attractive.

Digital Guidance Scales Differently

Once a correctly configured drill design is available to the machine, the operator can navigate through many planned positions without requiring each coordinate to be physically represented by a peg.

The survey workload does not disappear.

But the relationship between the number of holes and the amount of physical field set-out can change significantly.

That becomes more important as drill volumes increase.

Lost and Damaged Survey Pegs

One of the limitations of physical set-out is obvious.

The peg is in the production area.

Mining equipment may move through the drill pattern before drilling begins.

Set-out marks can potentially be:

  • Driven over
  • Buried
  • Covered
  • Knocked out
  • Disturbed
  • Difficult to identify
  • Removed during site preparation

When that happens, a hole may need to be re-established.

The digital coordinate, however, still exists in the design.

With a correctly configured blast hole GPS guidance system, the machine can navigate toward that coordinate without relying solely on a physical mark remaining in place.

Time Spent Finding Hole Locations

Physical set-out also creates a navigation task for the operator.

The operator has to determine:

  • Which hole is next
  • Where the mark is
  • Which mark belongs to which hole
  • How to travel efficiently through the pattern

This can become more challenging if marks are difficult to see.

With digital machine guidance, the drill pattern is displayed relative to the machine.

The operator can see the planned locations digitally and navigate accordingly.

Side-by-Side Comparison

Traditional Survey Set-OutBlast Hole GPS Guidance
Individual holes physically markedHoles displayed digitally
Operator locates pegs or marksOperator navigates using in-cab guidance
Marks can be damaged or lostDigital coordinates remain in design
Survey effort grows with physical set-out volumeMore survey effort can shift toward control and verification
Familiar field processMore digital workflow
Physical mark provides visual referenceMachine position compared directly with design
Re-set-out may be requiredDesigned point can remain available digitally
Less dependence on machine guidance hardwareRequires GNSS, calibration and reliable corrections

Neither workflow removes the need for good survey control.

The difference is how the drill position is transferred from design to machine.

How GNSS Determines the Drill Position

A blast-hole guidance system needs more than a GPS coordinate.

The system must determine:

  • GNSS antenna position
  • Machine heading or orientation
  • Machine geometry
  • Drill reference position
  • Designed target coordinate

These elements are combined by the guidance software.

The system can then calculate the difference between the current drill position and the planned hole.

Why RTK Is Required

Standard navigation GPS is generally not accurate enough for precision machine guidance.

Drill guidance typically relies on RTK GNSS corrections.

Corrections may be provided through:

  • Local base stations
  • Mine-site GNSS infrastructure
  • UHF radio
  • NTRIP
  • Compatible correction networks

This gives the machine the high-accuracy positioning information required for guidance.

Machine Calibration Matters

Survey set-out physically establishes the designed location in the field.

GNSS guidance takes a different route.

It calculates where the drill point is from the position of the installed GNSS hardware.

That means the system needs accurate machine measurements.

If an antenna is mounted away from the drilling point, the guidance system needs to know that geometric relationship.

Incorrect measurements can create a repeatable positioning error.

This is why machine calibration is just as important as GNSS accuracy.

RTK Fixed Is Not the Same as Verified Accuracy

An operator may see RTK Fixed and assume the system is correct.

But RTK Fixed only tells part of the story.

The GNSS receiver may know the antenna position accurately while the final drill position is wrong because of:

  • Incorrect antenna offsets
  • Incorrect machine calibration
  • Sensor error
  • Wrong project
  • Incorrect design revision
  • Coordinate-system problems
  • Site localisation errors
  • Base station position errors

A proper machine-guidance workflow still requires verification.

Independent Survey Checks Remain Essential

A newly installed drill guidance system should be checked against independent survey.

This confirms that the complete machine guidance solution agrees with known project control.

Verification should also be considered after events such as:

  • GNSS antennas being moved
  • Sensor replacement
  • Structural repairs
  • Machine modifications
  • Recalibration
  • Configuration changes
  • Unexpected accuracy complaints

This is where survey remains a critical part of the digital drilling workflow.

Survey Changes From Set-Out to Control

The biggest workflow shift is not the removal of survey.

It is the change in where survey effort is applied.

Traditional process:

Survey marks every hole.

Digital guidance process:

Survey establishes and verifies the positioning framework that allows the machine to locate the holes.

That can free survey resources for higher-value work.

Potential Productivity Benefits

The commercial value of blast hole GPS guidance can come from several areas.

Reduced Set-Out Work

Fewer individual field marks may be required.

Less Re-Set-Out

Missing or damaged pegs do not necessarily require the same response if the digital position remains available and the machine system is verified.

Reduced Drill Waiting Time

If a drill is waiting for set-out, production can be delayed.

Digital guidance can reduce some of this dependency.

Faster Navigation Between Holes

Operators can see the next target digitally.

Better Use of Survey Resources

Surveyors can spend more time on project control, QA and verification.

Blast Hole GPS Guidance and Drill Utilisation

Drill rigs are production assets.

A machine that is parked waiting for the next area to be set out is not drilling.

The value of guidance therefore should not be measured only by survey savings.

It should also consider:

  • Drill utilisation
  • Production delays
  • Mobilisation
  • Shift productivity
  • Crew coordination

If guidance allows drilling operations to move more efficiently from one designed location to the next, the effect can extend beyond the survey department.

What Happens During Design Changes?

Drill designs can change.

With physical set-out, revised positions may require field marks to be changed or re-established.

With a digital workflow, revised design information can potentially be updated within the machine-guidance environment.

The exact process depends on the software and site procedures.

Strong revision control remains essential.

The operator must always know that the correct design is loaded.

The Risk of the Wrong Digital Design

Digital workflows create different risks.

A physical peg can be wrong.

A digital file can also be wrong.

If the wrong design or revision is loaded, a highly accurate machine can precisely navigate to the wrong location.

This is why digital guidance needs good data-management procedures.

Sites should consider:

  • File naming
  • Revision control
  • Operator confirmation
  • Project selection
  • Design approval
  • Change management

Machine guidance improves the transfer of design information, but it does not eliminate the need to manage that information correctly.

Coordinate Systems Become More Important

With physical set-out, the surveyor resolves much of the coordinate-system complexity before the operator sees the mark.

With machine guidance, the machine itself operates within the project coordinate framework.

This makes correct configuration critical.

Problems with:

  • Localisation
  • Coordinate systems
  • Grid transformations
  • Project setup
  • Base coordinates

can affect machine guidance.

The digital workflow therefore requires stronger understanding of the full positioning chain.

Base Station Errors Affect the Whole System

If a local RTK base is established incorrectly, the machine can potentially produce repeatable but incorrect positions.

This is one reason survey control remains essential.

A consistent result is not necessarily a correct result.

The reference itself must be verified.

Physical Set-Out Can Still Be Useful

Digital guidance does not mean physical marks should never be used.

Some projects may use a hybrid workflow.

For example:

  • Key holes may be physically verified.
  • Start points may be marked.
  • Survey checks may be completed through the pattern.
  • Physical marks may be used during commissioning.
  • Selected holes may be independently checked.

The correct approach depends on the site’s procedures and risk controls.

Hybrid Survey and GNSS Workflows

For many operations, the strongest solution may be a combination of both technologies.

Machine guidance handles routine positioning.

Survey provides:

  • Control
  • Verification
  • Independent checks
  • QA
  • Troubleshooting

This retains survey oversight while reducing repetitive field set-out.

Blast-Hole GPS Guidance for Contractors

The advantages can be particularly relevant to mining contractors.

Contractors often need to:

  • Mobilise between sites
  • Work with different survey teams
  • Connect to different RTK systems
  • Operate mixed drill fleets
  • Meet varying project requirements

A digital guidance platform can help standardise the machine-side workflow.

However, site compatibility becomes important.

Check RTK Compatibility Before Mobilisation

A drill rig may work perfectly on one site and fail to receive corrections on another.

Mining contractors should confirm:

  • Base manufacturer
  • Correction format
  • UHF protocol
  • Frequency
  • Channel spacing
  • Baud/data settings
  • FEC settings where relevant
  • NTRIP availability

before mobilisation.

Saying that a receiver supports RTK or a particular correction format does not automatically guarantee that it will communicate with every site radio configuration.

Retrofit Blast-Hole GPS Guidance

Existing drill rigs can potentially be fitted with aftermarket machine guidance.

This can be attractive where:

  • The drill still has substantial service life
  • The OEM system is unavailable
  • The fleet contains different machine brands
  • The contractor wants a common guidance platform

A retrofit still needs proper:

  • GNSS installation
  • Machine measure-up
  • Calibration
  • RTK setup
  • Commissioning
  • Independent verification

The machine needs to be treated as a complete positioning system.

Stonex Blast-Hole GPS Guidance

Stonex machine-guidance technology provides a retrofit option for suitable drill-rig applications.

A Stonex drill guidance project can be developed around:

  • Existing drill rig
  • Required GNSS configuration
  • Machine geometry
  • Digital drill design
  • RTK infrastructure
  • Operator interface
  • Calibration
  • Verification

For Australian mining contractors, the ability to retrofit guidance can be particularly useful when there is a need to upgrade existing machines rather than replace them solely to obtain digital positioning.

Traditional Survey vs GPS Guidance: Which Is More Accurate?

This is not a useful question in isolation.

Both methods can produce high-quality positioning when correctly established.

The more important distinction is where the accuracy is controlled.

Traditional Set-Out

The surveyor establishes a physical point from the project control.

The drill operator positions against that physical reference.

GPS Guidance

The machine continuously calculates its position relative to the digital design.

Accuracy depends on the complete GNSS, machine-calibration and project-control chain.

Neither method should be assumed to be correct without appropriate QA.

Which Is More Efficient?

This depends heavily on drilling volume.

For a small number of holes, traditional set-out may be straightforward and efficient.

For large or repeated drill patterns, the economics can shift.

As the number of holes increases, repetitive physical set-out becomes a larger task.

Digital guidance can become more attractive because the machine can navigate through the design without requiring each hole to be represented physically.

A Simple Example

Consider a drill program with 1,000 planned holes.

Traditional Workflow

Survey may need to physically establish a large proportion of those positions.

Some marks may later require replacement.

Operators need to identify and locate the marks.

Digital Guidance Workflow

The design is loaded to the machine.

The drill navigates digitally between planned coordinates.

Survey focuses more heavily on control, checks and QA.

This does not mean there is zero field survey.

It means the 1,000 design coordinates do not necessarily require 1,000 physical marks.

That is the core productivity opportunity.

When Traditional Survey Set-Out May Still Make Sense

Traditional set-out may remain appropriate where:

  • Drill volumes are small
  • The project is short
  • Machines are not guidance-equipped
  • RTK infrastructure is unavailable
  • Digital workflows are not established
  • Site procedures require physical marks

Technology should be selected around the project, not simply because it exists.

When Blast Hole GPS Guidance Becomes Attractive

GPS guidance becomes particularly compelling where there are:

  • Large drill patterns
  • Repeated blasting programs
  • Significant survey workload
  • Lost or damaged set-out
  • Existing RTK infrastructure
  • Multiple guidance-ready drill rigs
  • Long-term projects
  • A requirement for digital workflow improvement

The larger and more repetitive the drilling operation, the stronger the potential business case can become.

GNSS vs Traditional Survey Set-Out: The Bottom Line

Traditional survey set-out remains a proven and accurate way of transferring drill designs into the field.

Blast hole GPS guidance does not make survey obsolete.

It changes how the design reaches the drill rig.

Traditional workflow:

Design → Survey → Physical Mark → Drill

GNSS-guided workflow:

Design → Digital Data → Drill Guidance → Verification → Drill

The main opportunity is reducing repetitive physical set-out while keeping strong survey control behind the machine-guidance system.

For mining contractors, that can mean:

  • Fewer physical marks
  • Less disruption from lost pegs
  • More direct navigation between holes
  • Reduced dependence on repeated set-out
  • Better utilisation of survey resources
  • A more digital connection between engineering and production

The strongest system is not one that removes survey.

It is one where survey and machine guidance work together.

Survey establishes and verifies the project reference.

GNSS tells the machine where it is.

The digital design tells the operator where to go.

That is the foundation of an effective blast-hole GPS guidance workflow.

Frequently Asked Questions About Blast Hole GPS Guidance

What is blast hole GPS guidance?

Blast hole GPS guidance uses high-accuracy GNSS, machine calibration and digital drill designs to guide a drill rig toward planned hole positions.

Does GPS drill guidance replace survey set-out?

It can reduce reliance on physical hole set-out, but survey remains essential for control, verification, coordinate systems and quality assurance.

Is blast hole GPS guidance more accurate than survey pegs?

Both approaches can provide accurate positioning when properly established. GPS guidance accuracy depends on GNSS, machine calibration, project coordinates, design information and verification.

Can drill rigs navigate directly to holes without pegs?

Yes, a correctly configured machine-guidance system can allow the operator to navigate toward digitally designed coordinates without relying solely on physical hole marks.

What happens if a survey peg is destroyed?

With traditional set-out, the point may need to be re-established. With verified digital guidance, the designed coordinate remains available within the machine system.

Does blast hole GPS guidance require RTK?

Precision machine guidance generally requires suitable high-accuracy correction information, commonly using RTK.

Can existing drill rigs be fitted with GPS guidance?

Suitable drill rigs can potentially be retrofitted with aftermarket guidance systems.

Does RTK Fixed guarantee the hole position is correct?

No. Overall accuracy also depends on machine calibration, antenna offsets, coordinate systems, localisation, design data and other factors.

Can Stonex be used for blast-hole GPS guidance?

Stonex machine-guidance technology can be configured for suitable drill-rig positioning applications, with the final system depending on the machine and project requirements.