Coordinate Systems and GDA2020 for Surveyors

The error that looks like nothing
Datum mistakes are the most expensive category of survey error because they don’t look like errors.
Everything is internally consistent. The equipment reports full accuracy. The data is clean. It’s just all in the wrong place, by a consistent amount, and nobody notices until it’s compared against something else.
The Australian situation
GDA94 — the Geocentric Datum of Australia 1994, the previous national datum.
GDA2020 — the current national datum, which accounts for the continental plate movement that has occurred since GDA94 was established.
The difference between them is roughly 1.8 metres. That is the problem in one number: large enough to matter enormously, small enough that a plan in the wrong datum still looks broadly plausible.
ATRF — the Australian Terrestrial Reference Frame, a time-dependent frame, relevant to certain applications.
MGA zones — the Map Grid of Australia projection, in zones. Work near a zone boundary needs care about which zone the project uses.
AHD — the Australian Height Datum, for heights. Note that horizontal and vertical datums are separate questions, and getting one right doesn’t mean you’ve got the other right.
Where mistakes happen
Design in one datum, survey in another. The most common. The design was produced in GDA94, the survey is in GDA2020, and the difference is built.
Correction service datum assumptions. A network correction service delivers positions in a particular frame. If your project expects a different one, you need to know.
Old control mixed with new. Control established years ago in GDA94 used alongside GDA2020 observations.
Zone confusion. Work spanning or near an MGA zone boundary, with different parts in different zones.
Height datum confusion. Ellipsoidal heights from GNSS treated as AHD heights, or a geoid model not applied.
Localisation applied inconsistently. A site calibration used for some work and not others.
The discipline that prevents it

  1. Establish the project datum in writing at the start. Horizontal datum, projection and zone, and vertical datum. Written into the project documentation, not assumed.
  2. Check every incoming dataset. Design files, existing survey, client-supplied control. What datum is each in? Don’t assume, and don’t accept “it should be” — check it against something known.
  3. Verify against known control. The practical safeguard. Occupy a known point of established coordinates and compare. A datum error shows up immediately as a systematic offset.
  4. Record what you did. Which datum, which transformation, which geoid model, which epoch where relevant. This documentation is what lets someone else use your work correctly.
  5. Be explicit on deliverables. Every plan, every file, every coordinate list should state the datum, projection, zone and height datum. A coordinate without a stated datum is not a coordinate.
    Localisation versus working in a projection
    Two approaches, often confused.
    Working in a defined projection — MGA in the appropriate zone, with a geoid model for heights. Coordinates are in a recognised national system, comparable with anything else in the same system.
    Localisation — computing a transformation between GNSS positions and a local site coordinate system, from observations on local control. Produces coordinates in the site’s own system, which may not relate simply to anything national.
    Localisation suits sites with an established local grid, or where the project was designed in one. Working in MGA suits work that needs to relate to national data and other projects.
    Both are legitimate. Mixing them without realising is where trouble starts.