Hemisphere Installation and Calibration
Two milestones, not one
Installation means the hardware is fitted. Commissioning means the system produces accurate output.
Conflating them is how contractors end up with a system that is technically installed and practically unusable — and how a supplier ends up with a customer who thinks the product is inaccurate when the setup was rushed.
Red Edge provides installation, calibration, training, preventative maintenance and remote/field support for Hemisphere systems. The calibration half is where accuracy comes from.
The installation
Sensor mounting. Boom, stick, bucket and chassis on an excavator; blade position sensors on a dozer. Secure, correctly positioned, protected from strikes.
Receiver and antennas. Mounted with adequate sky view, following the specified geometry where heading depends on antenna separation.
Display. Positioned so it is visible at a glance without obstructing the operator’s view of the work. A decision made once and lived with for years.
Cabling. Routed away from pinch points, heat and chafe. Hemisphere’s single-cable connection between receiver and display reduces this work and reduces the failure surface. [MFR]
Machine calibration
The system needs the machine’s actual geometry — real measurements of the machine in front of it, not nominal dimensions from a brochure.
Machine dimensions. Boom, stick and mounting point measurements, taken accurately.
Attachment geometry. Every bucket or blade in regular use, measured and entered.
Sensor positions. Where each sensor sits relative to the geometry.
Antenna positions. Where the antennas sit relative to the machine, and their separation.
A dimension entered 20mm out means every measurement is 20mm out. Consistently. With no error indication.
The attachment library
The most valuable hour of commissioning and the most commonly skipped.
GradeMetrix supports pre-measuring and saving bucket configurations for quick selection when changing attachments. [MFR]
Build the complete library at commissioning — every bucket in regular use, measured, configured, named so the operator can identify them without guessing.
Doing this later, on the day a bucket is first needed, by whoever is available, under time pressure, is how wrong configurations get entered. And wrong attachment selection is the leading cause of accuracy complaints across every brand of machine control.
Verification across the working range
Calibration is not complete until verified against something independent.
Machine positioned at a known point or against a known surface
System reading compared against the known value
Tested at several positions across the working range, not one
Result within tolerance, and recorded
Only then released for production work
Point 3 matters more than it looks. Because an excavator’s position calculation chains angles along the arm, a small angular error becomes a larger positional error at full reach. A system checked only at a comfortable mid-position can look fine and be well out extended.
If you’re running full 3D
Machine calibration is only half of it. Site calibration ties GNSS positioning to the site coordinate system, and it is the highest-consequence step in the whole setup — a bad one produces confident, precise, consistently wrong work with no error indication.
In a 2.5D workflow this step doesn’t exist, which is a meaningful risk reduction as well as a time saving.
Ongoing verification
Commissioning establishes accuracy. Keeping it needs routine:
Pre-start known-point check with a defined tolerance, a recorded result and a stated action on failure.
Recalibration after events — component replacement, repair, impact, or work on machine geometry.
Periodic verification at a set interval regardless.
Why this connects to everything
The value case rests on people trusting the system enough to stop checking manually.
They trust it only if it is right, and it is only right if properly calibrated and routinely verified. A system commissioned in a hurry produces a site that never quite trusts it — which keeps every cost and every exposure the system was meant to remove.[VERIFY] — confirm what verification standard Red Edge applies at commissioning and what documentation the customer receives. A documented verification certificate is a genuine differentiator and worth stating if you do it.