Moving a Stonex System Between Machines

The flexibility, stated accurately
Stonex material indicates STX-MC can store multiple machine profiles — up to four — with the display and GNSS antennas movable between machines, while the sensors must remain fixed to each machine and properly calibrated. \[MFR]
That distinction is the whole thing, so it is worth stating plainly rather than letting “portable system” do the work.
What moves and what doesn’t
Moves: the display unit and the GNSS antennas.
Stays: the angle sensors, fixed to each machine’s geometry and calibrated to it.
Stored: the machine profile — the configuration describing that machine’s dimensions, sensor positions and attachment library.
What this means commercially
Each machine still needs its own sensors, mounting and calibration. That is the per-machine cost and it does not go away.
What can potentially be shared is the display and antennas — genuinely useful where a fleet has machines that don’t all need guidance simultaneously. A contractor with four excavators where two are on guidance-relevant work at any time may not need four full configurations.
\[VERIFY] — confirm the component split and cost implications for the configurations Red Edge supplies, so this can be stated in real terms rather than in principle.
When it makes sense
Machines used seasonally or intermittently on guidance-relevant work.
A fleet larger than the number of guided jobs running at once.
Trialling before committing — fitting sensors to several machines and moving one display around while proving the case.
A machine out of service — moving the display and antennas to a replacement rather than standing the capability down.
When it doesn’t
Machines that all need guidance at once. Obviously.
Frequent swapping. Every move is a task plus a verification step. Moving daily costs more time than a second display saves.
Where the risk isn’t managed. See below.
The verification step you cannot skip
The obvious failure mode: the display is moved, the wrong machine profile is active, and the system produces confident output based on a different machine’s geometry.
Nothing looks wrong. The display is normal, the accuracy indication is fine, and the work is wrong.
Every transfer needs a defined procedure:
Physically transfer display and antennas, mounted correctly
Select the correct machine profile — deliberately confirmed, not assumed
Verify against a known point or known surface
Test at more than one position across the working range
Record the check and the result
Only then resume work
Write this into your standard procedures rather than relying on the operator remembering. The consequence of getting it wrong is a shift of accurate, expensive, wrong work.
The profile limit
Four profiles is a real constraint on a larger fleet. A contractor with six or eight machines needs a plan for which machines are profiled, and a process for changing them.
\[VERIFY] — confirm the current profile limit and whether profiles can be exported, stored and reloaded.
CTA: Ask Red Edge Resources about the transfer procedure and verification standard for your configuration.