Machine Control Installation: Why Professional Commissioning
Machine Control Installation: Why Professional Commissioning Matters
Accurate Machine Guidance Starts with Correct Installation
Machine control technology can transform how civil construction, mining and earthmoving projects are completed.
When correctly installed and commissioned, a machine control system can provide operators with real-time information about:
- Position
- Elevation
- Depth
- Slope
- Alignment
- Cut and fill
- Bucket or blade location
- Digital design surfaces
However, machine control accuracy does not come from the hardware alone.
A high-quality display, GNSS receiver and sensor package can still provide inaccurate or unreliable guidance when the installation has not been properly measured, configured, calibrated and tested.
This is why professional machine control commissioning matters.
Commissioning confirms that every part of the system—from the GNSS antennas and machine sensors to the attachment profiles, RTK corrections and digital project files—is working together correctly.
At Red Edge Resources, machine control installation is supported by practical experience deploying machine guidance, surveying and communications systems across Australian mining and civil environments. Red Edge also provides installation, preventative maintenance, operator training and ongoing technical support.
What Is Machine Control Commissioning?
Machine control installation and machine control commissioning are closely related, but they are not the same process.
Machine Control Installation
Installation generally includes:
- Mounting the display
- Installing sensors
- Fitting GNSS antennas
- Mounting the GNSS receiver
- Installing radio or cellular equipment
- Routing cables
- Connecting power
- Connecting system components
Machine Control Commissioning
Commissioning verifies that the installed system is correctly configured and ready for production.
It may include:
- Measuring the machine
- Measuring attachments
- Entering GNSS antenna offsets
- Configuring sensors
- Setting up RTK corrections
- Calibrating the machine
- Loading digital project files
- Checking coordinate systems
- Testing accuracy against known control
- Verifying hydraulic response
- Training operators
- Recording the completed configuration
Installation puts the equipment onto the machine.
Commissioning confirms that the operator can trust the guidance.
Why Correct Machine Control Installation Matters
A machine control system calculates the location of the machine’s working point using several connected measurements and data sources.
Depending on the application, the system may rely on:
- One or two GNSS antennas
- GNSS receiver
- RTK correction service
- Radio antenna or cellular modem
- Boom sensor
- Stick or dipper sensor
- Bucket sensor
- Blade sensor
- Machine-body sensor
- Pitch and roll sensor
- Tilt or rotation sensor
- Machine measurements
- Attachment dimensions
- Digital project files
- Site localisation
- Hydraulic control modules
A problem with any one of these elements can affect the final position shown to the operator.
For example:
- An incorrect antenna offset can affect machine position.
- A flexible sensor bracket can introduce changing errors.
- Incorrect bucket measurements can alter the displayed cutting edge.
- Poorly protected wiring can cause intermittent sensor faults.
- Incorrect RTK settings can prevent a stable fixed position.
- The wrong coordinate system can place the machine away from the design.
- Poor hydraulic tuning can cause a blade to overshoot grade.
Professional commissioning considers the complete system rather than treating the hardware as separate components.
Installation Versus Professional Commissioning
| Basic Installation | Professional Commissioning |
|---|---|
| Hardware is attached | Hardware placement is inspected and verified |
| Sensors are connected | Sensor orientation and communication are tested |
| GNSS antennas are mounted | Antenna position and offsets are measured |
| Wiring is installed | Wiring is protected and tested through machine movement |
| Display powers on | Correct machine profile and software settings are confirmed |
| Measurements are entered | Measurements are physically checked |
| Attachment is selected | Attachment geometry is measured and tested |
| RTK connects | Fixed solution stability is verified |
| Project file loads | Coordinates, surface and revision are checked |
| Calibration process completes | Accuracy is tested against known control |
| Basic handover occurs | Operator training and fault recognition are completed |
| Limited records are retained | Installation and calibration details are documented |
A system can appear operational without being fully commissioned.
The display may turn on, receive GNSS corrections and show a design while still producing an incorrect bucket, blade or machine position.
What Professional Machine Control Commissioning Should Include
1. Machine and Application Assessment
Before installation begins, the machine control supplier should understand how the machine will be used.
The assessment should consider:
- Machine make and model
- Machine size
- Machine configuration
- Hydraulic capability
- Electrical system
- Attachment types
- Type of work
- Required tolerance
- Operator experience
- Project environment
- Existing GNSS equipment
- Available RTK correction source
A machine used for bulk excavation may require a different system configuration from a machine completing detailed drainage, final trim or precision grading.
The installation should be designed around the machine and application rather than applying a generic hardware layout.
2. Pre-Installation Inspection
The machine should be inspected before sensors, antennas and wiring are installed.
The installer should identify:
- Existing machine damage
- Structural modifications
- Hydraulic leaks
- Electrical problems
- Suitable bracket locations
- Cable-routing paths
- Potential impact areas
- Heat sources
- Moving components
- Existing accessories
- Attachment wear
- Service-access requirements
Identifying these conditions early helps avoid component damage and unreliable performance after installation.
3. Correct Sensor Placement
Machine control sensors measure the position and movement of components such as:
- Boom
- Stick
- Bucket
- Blade
- Mast
- Machine body
- Tilt mechanism
- Rotation mechanism
Sensors must be mounted on rigid brackets that remain stable during vibration and machine operation.
Sensor placement must account for:
- Machine geometry
- Full operating range
- Potential impact
- Cable movement
- Hydraulic hoses
- Heat
- Mud and debris
- Maintenance access
- Component protection
A sensor may be electronically accurate but still produce incorrect information when its bracket moves, flexes or has been positioned incorrectly.
4. GNSS Antenna Installation
GNSS antenna position is a critical part of a three-dimensional machine control installation.
The installer must consider:
- Clear visibility of the sky
- Antenna protection
- Structural rigidity
- Cable access
- Safe operator access
- Machine orientation
- Antenna separation
- Stored antenna offsets
- Potential impact points
On dual-antenna systems, the relationship between the two antennas may also be used to determine machine heading.
If an antenna or antenna mast moves after commissioning, the stored measurements may no longer represent the physical installation.
5. Wiring and Cable Protection
Machine control wiring operates in a demanding environment.
Cables may be exposed to:
- Constant vibration
- Boom or blade movement
- Hydraulic hose movement
- Dust
- Water
- Heat
- Oil
- Abrasion
- Pressure washing
- Pinching
- Impact
A professional installation should provide:
- Appropriate cable conduit
- Secure cable supports
- Connector protection
- Strain relief
- Safe bend radius
- Clearance from hot components
- Clearance from articulation points
- Service loops where required
- Access for future maintenance
The installer should operate the machine through its working range and verify that cables do not stretch, rub, catch or become pinched.
Poor wiring installation is a common cause of intermittent faults that only appear when the machine reaches a particular position.
6. Stable Electrical Integration
Displays, receivers, sensors, radios and communication modules require a stable electrical supply.
Professional electrical integration may include:
- Correct supply voltage
- Fuse protection
- Reliable earth connection
- Ignition switching
- Battery-isolator compatibility
- Connector sealing
- Surge protection
- Power-load assessment
Electrical problems can cause:
- Display restarts
- Receiver resets
- Sensor disconnections
- Communication failures
- Data loss
- Intermittent system behaviour
Power supply and grounding should be tested during commissioning rather than assumed to be correct.
Accurate Machine Measurements
Machine control software creates a digital representation of the physical machine.
Depending on the system, required measurements may include:
- Boom length
- Stick or dipper length
- Bucket dimensions
- Blade dimensions
- Pivot locations
- Machine centreline
- GNSS antenna offsets
- Sensor locations
- Quick-hitch geometry
- Tilt axis
- Rotation axis
Incorrect measurements can create an error that changes as the machine moves.
For example, an excavator may appear accurate close to the machine but become increasingly inaccurate at full reach when the boom or stick measurements are incorrect.
Machine-control setup therefore requires accurate machine measurement, sensor configuration and calibration—not merely installing the hardware. Red Edge describes its installation and training process as including independent installation, calibration, monitoring and troubleshooting support.
Attachment Measurement and Calibration
Attachment profiles are particularly important on excavators.
An excavator may use:
- General-purpose bucket
- Mud bucket
- Trenching bucket
- Rock bucket
- Batter bucket
- Tilt bucket
- Tiltrotator
- Ripper
- Compaction wheel
- Grab
- Custom attachment
Each attachment can have different:
- Length
- Width
- Cutting-edge position
- Pin location
- Quick-hitch relationship
- Tilt offset
- Rotation offset
If the attachment profile does not match the physical tool, the display may indicate that the bucket is on grade when the actual cutting edge is too high or too low.
Professional commissioning should include:
- Identifying each attachment
- Measuring the attachment
- Configuring the correct hitch relationship
- Defining the guided cutting point
- Naming the profile clearly
- Testing the attachment against known control
- Training the operator to select the correct profile
Attachments should also be rechecked after:
- Cutting-edge replacement
- Tooth replacement
- Bucket repairs
- Added wear plates
- Hitch replacement
- Structural modification
GNSS and RTK Commissioning
Three-dimensional machine control generally requires RTK corrections to provide the positioning accuracy needed for detailed machine guidance.
RTK corrections may come from:
- A local base station
- Site radio network
- Network RTK service
- Cellular correction service
- Internet-based correction source
Commissioning should confirm:
- GNSS receiver configuration
- Correction format
- Radio frequency
- Radio channel
- Cellular settings
- Antenna condition
- Base-station compatibility
- Correction age
- Stable fixed status
- Practical coverage across the work area
It is not enough for the display to briefly achieve RTK fixed.
The solution should remain stable while the machine moves, rotates and operates in the intended work area.
Stonex STX-DIG systems offered by Red Edge use GNSS positioning and digital designs to provide centimetre-level, three-dimensional excavator guidance.
Coordinate Systems and Site Localisation
A machine may have stable RTK fixed positioning while still being incorrect relative to the digital project.
This can occur when the wrong coordinate system, localisation or height reference is active.
Commissioning should verify:
- Horizontal coordinate system
- Vertical datum
- Geoid model
- Site localisation
- Control points
- Easting and northing
- Machine orientation
- Design position
- Known elevations
Warning signs of a coordinate-system problem include:
- The machine appearing outside the work area
- A rotated design
- Correct horizontal position but incorrect elevation
- Large constant cut-or-fill differences
- Design features not matching survey marks
- Machine movement appearing reversed on screen
Coordinate problems should be corrected at their source.
Arbitrary horizontal or vertical offsets may hide the original error and make future troubleshooting more difficult.
Digital Project File Verification
Machine control relies on digital information supplied to the display.
This may include:
- Design surfaces
- DXF linework
- LandXML data
- Alignments
- Points
- Drainage lines
- Road strings
- Boundaries
- Exclusion zones
Professional commissioning should confirm:
- Supported file format
- Correct project coordinates
- Current design revision
- Correct construction stage
- Surface integrity
- Layer visibility
- File naming
- Design coverage
- Data-transfer process
- Revision-control procedure
A project file may load successfully while still containing the wrong coordinate system, design stage or surface.
The commissioning process should therefore verify the data against known site information before production begins.
Machine Control Calibration
Calibration establishes the relationship between the physical machine and the digital system.
Depending on the machine, calibration may include:
- Sensor zero positions
- Boom calibration
- Stick calibration
- Bucket calibration
- Blade calibration
- Pitch and roll
- Machine-body alignment
- Antenna alignment
- Tilt calibration
- Rotation calibration
- Hydraulic response
- Control direction
The calibration procedure should follow the equipment manufacturer’s requirements.
However, completion of the software calibration process does not automatically prove that the final result is accurate.
The system must also be tested against an independent reference.
Accuracy Verification
A professionally commissioned system should be checked under realistic working conditions.
Accuracy verification may include:
- Known-point check
- Bucket-tip check
- Blade-height check
- Slope check
- Tilt check
- Rotation check
- Multiple machine orientations
- Multiple attachment positions
- Comparison with survey control
- Repeated measurements
- RTK stability testing
For an excavator, the bucket may be checked:
- Close to the machine
- At normal operating reach
- At extended reach
- At different bucket angles
- With the machine facing different directions
- With different attachments
A machine that is accurate in only one position has not been fully verified.
Red Edge’s technical repair and diagnostic services include system analysis, performance testing and calibration verification.
Hydraulic Machine Control Commissioning
Some machine control systems interact directly with the machine hydraulics to provide automatic blade or attachment control.
Hydraulic commissioning may include:
- Valve compatibility
- Control direction
- Minimum current
- Maximum current
- Hydraulic deadband
- Response speed
- Sensor response
- Automatic mode activation
- Manual override
- Safety interlocks
Poor hydraulic commissioning can result in:
- Overshooting grade
- Oscillation
- Slow response
- Aggressive movement
- Inconsistent control
- Unnecessary machine wear
- Poor operator confidence
Automatic control should be tuned and tested under controlled conditions before full production use.
Operator Training Is Part of Commissioning
A machine control installation is not complete until the operator understands how to use and check the system.
Operator commissioning should cover:
- Starting the system
- Selecting the correct machine profile
- Selecting attachments
- Loading projects
- Confirming the design revision
- Understanding cut and fill
- Checking GNSS status
- Understanding fixed and float RTK
- Completing a known-point check
- Recognising warning messages
- Reporting faults
- Understanding stop-work conditions
- Protecting installed equipment
Operators should also understand that RTK fixed status does not automatically confirm:
- Correct attachment profile
- Correct machine measurements
- Correct calibration
- Correct project file
- Correct localisation
Training helps operators use the technology as an informed construction tool rather than following the display without verification.
Commissioning Documentation
A properly commissioned machine control system should have a clear installation and configuration record.
Documentation may include:
- Machine make and model
- Machine identification
- Installed system
- Component serial numbers
- Sensor locations
- Antenna locations
- GNSS antenna offsets
- Machine measurements
- Attachment measurements
- Software versions
- Firmware versions
- RTK settings
- Radio configuration
- Calibration date
- Calibration results
- Known-point results
- Operator training completed
- Outstanding recommendations
These records become valuable when:
- Troubleshooting faults
- Replacing components
- Completing recalibration
- Adding attachments
- Transferring hardware
- Investigating warranty issues
- Reviewing equipment history
Without documentation, technicians may need to repeat measurements and configuration checks before the original fault can be diagnosed.
Common Risks of Poor Machine Control Installation
Inconsistent Accuracy
The machine may appear correct in one position but become inaccurate as the boom, stick, bucket or blade moves.
Potential causes include:
- Incorrect machine measurements
- Flexible sensor brackets
- Poor calibration
- Incorrect antenna offsets
- Loose hardware
Intermittent Sensor Faults
Poor wiring routes may cause cables to stretch, rub or disconnect as the machine moves.
Unstable RTK Performance
Incorrect antenna installation, radio settings or correction configuration can cause:
- Frequent float status
- Slow RTK fixed solutions
- Correction dropouts
- Restricted operating range
- Inconsistent positioning
Incorrect Attachments
A generic attachment profile may produce incorrect guidance across different buckets or tools.
Rework and Over-Excavation
Incorrect machine guidance may result in:
- Digging below design
- Leaving excess material
- Incorrect trench depth
- Incorrect slope
- Poor final trim
- Material replacement
- Additional survey attendance
Loss of Operator Confidence
Operators may stop trusting the system when machine guidance repeatedly disagrees with survey checks.
This can lead to:
- Reduced technology use
- Unnecessary survey set-out
- Unofficial offsets
- Slower manual workflows
- Poor return on investment
Basic Installation Versus Professional Commissioning
| Area | Incomplete Installation | Professional Commissioning |
| System selection | Based mainly on hardware availability | Matched to machine, application and accuracy requirements |
| Sensor mounts | Generic mounting | Rigid, protected and machine-specific |
| Wiring | Components connected | Protected routing tested through machine movement |
| Measurements | Estimated or entered quickly | Physically measured and independently checked |
| Attachments | One generic profile | Individual profiles measured and verified |
| GNSS | Receiver obtains position | Antennas, offsets and positioning stability checked |
| RTK | Corrections connect | Fixed status tested throughout the work area |
| Digital design | File loads | Revision, coordinates and surface verified |
| Calibration | Software procedure completed | Result tested against known control |
| Training | Basic display overview | Daily checks, workflows and fault recognition |
| Documentation | Limited records | Complete installation and calibration record |
| Support | Reactive assistance | Defined remote and field-support pathway |
The cheapest installation price may not produce the lowest total ownership cost.
Rework, downtime, repeated calibrations and operator distrust can quickly exceed the initial saving.
Can Machine Control Be Self-Installed?
Some systems are designed to support contractor or technician self-installation.
Self-installation may be practical when:
- The system is designed for simplified installation
- The contractor has competent technical staff
- Mounting requirements are straightforward
- Machine measurements are clearly understood
- Hydraulic integration is not complex
- Remote support is available
- Accuracy can be independently verified
Red Edge provides self-installation pathways and training for suitable systems, including guidance on installation, calibration, monitoring and troubleshooting.
However, self-installation should never mean skipping commissioning.
Whether the hardware is installed by the contractor or a field technician, the completed system should still be:
- Accurately measured
- Correctly configured
- Calibrated
- Accuracy tested
- Documented
- Supported with operator training
When Professional Installation Is Strongly Recommended
Professional installation and commissioning are especially important when:
- Installing full three-dimensional machine control
- Integrating hydraulic automatic control
- Equipping a high-production machine
- Working to tight project tolerances
- Installing dual-GNSS antennas
- Fitting tilt or rotation attachments
- Configuring multiple attachments
- Working in remote mining environments
- Connecting to a site-wide RTK network
- Standardising technology across a fleet
- Meeting client quality-assurance requirements
- Installing on a complex or modified machine
The greater the production and quality risk, the stronger the case for professional commissioning.
Commissioning Different Machine Types
Excavator Machine Control Installation
Excavator commissioning may include:
- Boom measurement
- Stick measurement
- Bucket and attachment profiles
- Quick-hitch configuration
- Boom sensor calibration
- Stick sensor calibration
- Bucket sensor calibration
- Tilt or rotation configuration
- GNSS antenna offsets
- Machine-body alignment
- Bucket-tip accuracy testing
Explore STX-DIG Excavator Machine Control
Dozer Machine Control Installation
Dozer commissioning may include:
- Blade geometry
- GNSS mast position
- Blade sensor calibration
- Cross-slope calibration
- Machine pitch and roll
- Hydraulic-control tuning
- Blade-height testing
Explore Dozer Machine Control Solutions
Grader Machine Control Installation
Grader commissioning may include:
- Mainfall sensors
- Cross-slope sensors
- Blade rotation
- GNSS antenna position
- Hydraulic response
- Design alignment
- Final-trim accuracy testing
Drill and Piling Guidance Installation
Drill and piling commissioning may include:
- Mast alignment
- Pitch and roll
- GNSS antenna offsets
- Machine heading
- Depth reference
- Design plan setup
- Coordinate verification
- Reporting configuration
- Position and alignment testing
What Happens After Commissioning?
Machine control commissioning should begin an ongoing support relationship rather than end it.
After installation, contractors may require:
- Remote technical support
- Field service
- Additional attachment profiles
- RTK troubleshooting
- Operator refresher training
- Software updates
- Firmware updates
- Preventative maintenance
- Replacement components
- Accuracy checks
- System upgrades
Red Edge Resources offers machine control installation, preventative maintenance, training, consulting and ongoing technical support.
Preventative Maintenance Protects Commissioning Accuracy
Even a correctly commissioned system may change over time.
Accuracy can be affected by:
- Sensor movement
- Antenna movement
- Bracket damage
- Pin and bush wear
- Bucket repairs
- Cutting-edge replacement
- Wiring damage
- Machine structural repairs
- Software changes
- Hydraulic work
Daily operator checks and scheduled professional inspections help preserve the accuracy established during commissioning.
Related article:
Preventative Maintenance for Machine Control Systems
Questions to Ask a Machine Control Installer
Before approving a machine control installation, ask:
- Is this system suitable for the machine and application?
- Who will measure the machine?
- Which attachments are included?
- Will every attachment have its own profile?
- How will the sensors be protected?
- How will cables be routed?
- Is RTK setup included?
- Is coordinate-system verification included?
- Are project files included in commissioning?
- Will accuracy be checked against known control?
- Is hydraulic commissioning included?
- Is operator training included?
- Will the final setup be documented?
- What warranty applies?
- What remote support is available?
- What field support is available?
- Who completes future calibration?
- What happens after machine or attachment repairs?
A complete quotation should clearly separate:
- Equipment supply
- Installation
- Commissioning
- Calibration
- Training
- Travel
- Ongoing support
Machine Control Commissioning Checklist
| Commissioning Area | Required Outcome |
| Application assessment | System confirmed suitable for machine and work type |
| Physical installation | Components securely mounted and protected |
| Wiring | Correctly routed and tested through full movement |
| Power supply | Stable, fused and correctly grounded |
| Machine measurements | Physically measured and verified |
| Attachment profiles | Individually configured and tested |
| GNSS setup | Receiver and antennas correctly configured |
| RTK corrections | Stable fixed solution confirmed |
| Coordinate system | Correct horizontal and vertical reference |
| Digital project | Current design loaded and verified |
| Sensor calibration | Completed using the required procedure |
| Hydraulic control | Tuned and safely tested where applicable |
| Accuracy test | Checked against known site control |
| Operator training | Daily operation and fault recognition understood |
| Documentation | Configuration and results recorded |
| Support pathway | Technical contacts and procedures supplied |
Why Choose Red Edge Resources?
Red Edge Resources approaches machine control installation as a complete operational solution rather than a hardware-only transaction.
Our services include:
- Machine control system selection
- Pre-installation inspections
- Professional installation
- Machine measurement
- Attachment measurement
- Sensor configuration
- GNSS setup
- RTK commissioning
- Machine calibration
- Accuracy verification
- Operator training
- Remote technical support
- Field service
- Preventative maintenance
- System troubleshooting
- Fleet technology reviews
Red Edge’s machine control capability is supported by practical experience across mining and civil environments, alongside installation, training and ongoing technical support services.
Contact Red Edge Resources to discuss professional machine control installation, commissioning or calibration.
Frequently Asked Questions
What is machine control commissioning?
Machine control commissioning is the process of configuring, calibrating, testing and verifying the complete installed system.
It confirms that the machine, sensors, GNSS receiver, RTK corrections, attachment profiles and digital project data work together correctly.
Is machine control commissioning different from installation?
Yes.
Installation fits and connects the hardware. Commissioning verifies that the completed system is accurate, reliable and ready for production.
Does RTK fixed mean the machine is calibrated?
No.
RTK fixed confirms the quality of the GNSS positioning solution.
It does not confirm:
- Machine measurements
- Sensor calibration
- Attachment dimensions
- Antenna offsets
- Project revision
- Site localisation
Does every attachment need its own profile?
Each attachment with different geometry or a different cutting position should have its own accurate profile.
A generic profile should not be used across attachments with different dimensions.
Can machine control be self-installed?
Some systems can be self-installed by contractors with suitable technical capability and access to commissioning support.
The installation must still be measured, configured, calibrated and accuracy tested.
Should operators be involved in commissioning?
Yes, where practical.
Operator involvement allows training to be completed on the actual machine and helps establish the correct daily checks, attachment-selection process and fault-reporting workflow.
When should a machine control system be recommissioned?
Full or partial recommissioning may be required after:
- Sensor replacement
- GNSS antenna movement
- Bracket repairs
- Major machine repairs
- Hydraulic work
- Hardware transfer
- Attachment modification
- Significant software changes
- Persistent accuracy problems
What should be checked after installation?
The commissioning process should verify:
- Secure hardware
- Stable power
- Sensor communication
- Correct machine dimensions
- Correct attachment profiles
- Stable RTK fixed status
- Correct project coordinates
- Accurate bucket or blade position
- Operator understanding
Conclusion
Machine control installation is not complete when the hardware has been attached and the display powers on.
Reliable machine guidance requires the complete system to be:
- Correctly selected
- Securely mounted
- Accurately measured
- Properly configured
- Connected to stable RTK corrections
- Correctly calibrated
- Tested against known control
- Understood by the operator
- Documented for future support
Professional commissioning reduces the risk of incorrect measurements, unstable RTK, attachment errors, sensor problems, coordinate-system faults and recurring downtime.
More importantly, it provides a machine control system that operators can trust and the business can use to improve accuracy, productivity and project delivery.
At Red Edge Resources, we provide machine control installation, commissioning, calibration, training and technical support for Australian civil construction, mining and earthmoving operations.
Internal Links
Use these links naturally throughout the article:
- Red Edge Machine Control Solutions
https://rededgeresources.com.au/stonex-machine-control/ - Machine Control Services
https://rededgeresources.com.au/services/ - STX-DIG Excavator Machine Control
https://rededgeresources.com.au/stx-dig-excavators/ - Stonex 2D Excavator Machine Control
https://rededgeresources.com.au/stonex-2d-excavator-machine-control-australia-advanced-digging-guidance-technology/ - Dozer Machine Control Solutions
https://rededgeresources.com.au/dozer-solutions/ - Machine Control Self-Installation and Training
https://rededgeresources.com.au/how-contractors-can-successfully-install-their-own-machine-control-systems-with-red-edge-resources/ - Technical Repairs and Calibration
https://rededgeresources.com.au/technical-repairs/ - Common Excavator Machine Control Problems
https://rededgeresources.com.au/common-excavator-machine-control-problems/ - Excavator Machine Control Pre-Start Inspection
https://rededgeresources.com.au/excavator-machine-control-pre-start-inspection/ - Contact Red Edge Resources
https://rededgeresources.com.au/contact/
Excavator Machine Control Pre-Start Inspection Checklist |
A Practical Daily Checklist for Accurate and Reliable Excavation
An excavator machine control system can provide real-time guidance for depth, elevation, slope, alignment and bucket position.
However, operators should never assume the system is accurate simply because the display has powered on and is showing a design.
Reliable machine guidance depends on several connected elements working correctly, including:
- The physical machine
- Boom, stick and bucket sensors
- GNSS antennas and receivers
- RTK correction services
- Machine measurements
- Attachment profiles
- Site localisation
- Digital project files
- The operator’s system setup
A loose sensor, damaged cable, incorrect bucket profile or outdated design file may not stop the display from working. Instead, it may cause the system to present guidance that appears believable but does not accurately represent the physical bucket or current project design.
Completing a structured excavator machine control pre-start inspection helps operators identify these issues before excavation begins.
At Red Edge Resources, we provide machine control installation, calibration, preventative maintenance, training and ongoing technical support for systems operating in Australian civil, construction and mining environments.
Why Excavator Machine Control Pre-Starts Matter
An excavator machine control system calculates the position of the bucket cutting edge by combining information from multiple components.
Depending on the system, these may include:
- One or two GNSS antennas
- GNSS receiver
- RTK radio or cellular modem
- Boom sensor
- Stick or dipper sensor
- Bucket sensor
- Tilt or rotation sensor
- Machine-body sensor
- In-cab display
- Machine geometry
- Quick-hitch measurements
- Attachment dimensions
- Site coordinate system
- Digital design surface
The position shown on the display is only as reliable as the data being supplied to it.
For example:
- An incorrect bucket profile can produce the wrong cutting-edge position.
- A moved sensor can affect the calculated boom, stick or bucket angle.
- A loose GNSS antenna can change the relationship between the receiver and the machine.
- An unstable RTK solution can cause the calculated position to drift or jump.
- An incorrect localisation can place the machine in the wrong position relative to the design.
- A superseded project file can direct the operator towards outdated levels.
Daily checks therefore form part of the project’s quality-control process, not simply the machine’s maintenance routine.
Excavator Machine Control Pre-Start Checklist
| Inspection Item | What the Operator Should Confirm |
|---|---|
| Display startup | The display starts normally without repeated errors, freezing or restarting |
| Excavator profile | The correct machine configuration is active |
| Attachment profile | The selected bucket, ripper or attachment matches the one physically fitted |
| Quick-hitch profile | The correct quick hitch or coupler configuration is selected |
| Cutting edge | The bucket edge, teeth and wear plates have not changed since calibration |
| Sensors | Boom, stick, bucket and tilt sensors are secure and communicating |
| Sensor brackets | Brackets are tight, undamaged and have not moved |
| Wiring | Visible cables are not cut, pinched, stretched or disconnected |
| GNSS antennas | Antennas and mounting points are secure and visibly undamaged |
| RTK equipment | Radio antenna, modem or network connection is operating |
| GNSS position | The receiver is tracking satellites and producing a stable position |
| RTK status | The required fixed correction status has been achieved and remains stable |
| Project file | The correct project, design surface and revision are selected |
| Localisation | The correct site coordinate system and localisation are active |
| Bucket movement | The on-screen bucket follows the physical bucket smoothly |
| Known-point check | The bucket position agrees with established control within project tolerance |
| Cut-and-fill values | Displayed values appear reasonable for the work area |
| Fault handover | Previous shift faults, warnings or temporary repairs have been reviewed |
1. Complete a Visual Walk-Around
Before starting the machine control display, inspect the installed hardware during the excavator’s normal pre-start walk-around.
Check:
- GNSS antennas
- Antenna masts
- Sensor brackets
- External control modules
- Wiring harnesses
- Cable conduit
- Electrical connectors
- Radio antennas
- Display mounting
- Any recently repaired areas
Look for anything that appears different from the previous shift.
Warning signs include:
- A sensor sitting at a different angle
- A loose or missing mounting bolt
- A bent antenna mast
- A disconnected plug
- A cracked sensor or antenna housing
- Damaged cable protection
- Wiring hanging away from its normal position
- Excessive mud around a sensor
- Evidence of impact damage
- Repairs completed near the installed system
Visible damage should be reported before the operator begins relying on machine guidance.
2. Inspect the GNSS Antennas
The GNSS antennas establish the excavator’s position and, on dual-antenna systems, may also help determine the machine’s orientation.
Check that each antenna is:
- Firmly mounted
- In its normal position
- Free from cracks
- Connected correctly
- Clear of heavy material buildup
- Protected from branches, lifting chains and nearby equipment
- Not being used as a handhold
- Mounted on an undamaged bracket or mast
A small movement in an antenna mount may change the stored relationship between the GNSS position and the machine.
Do not reposition an antenna without confirming whether its measurements, offsets or calibration need to be updated.
Stonex excavator machine control solutions supplied by Red Edge use GNSS positioning and digital designs to provide real-time three-dimensional guidance to the operator.
3. Inspect the Boom, Stick and Bucket Sensors
Excavator machine control normally depends on sensors installed on or around the machine linkage.
These may include:
- Boom sensor
- Stick or dipper sensor
- Bucket sensor
- Machine-body sensor
- Tilt bucket sensor
- Rotation sensor
- Pitch and roll sensor
Check that each accessible sensor:
- Is securely attached
- Has not moved on its bracket
- Has no visible impact damage
- Has a secure connector
- Has protected wiring
- Is not covered by excessive mud or material
- Appears consistent with its normal installed position
Operators should not loosen or adjust sensors to make the displayed bucket position agree with an expected level.
Moving a sensor may change the machine calibration and introduce additional errors.
4. Inspect Wiring and Connectors
Machine control wiring on an excavator is exposed to constant articulation and vibration.
The most vulnerable locations are often around:
- Boom pivot points
- Stick joints
- Bucket linkage
- Quick hitches
- Tiltrotators
- Hydraulic hose runs
- Cab entry points
- GNSS antenna mounts
Inspect visible cables for:
- Cuts
- Abrasion
- Crushing
- Stretching
- Pinching
- Exposed conductors
- Loose connectors
- Broken conduit
- Contact with hydraulic hoses
- Contact with sharp brackets
- Contact with hot components
- Hydraulic oil contamination
An intermittent wiring fault may not be apparent while the machine is stationary.
A cable may disconnect only when the boom, stick or bucket reaches a particular position. This is why the system should also be observed while the machine moves through its working range.
5. Start the Display and Review Warnings
Start the machine control display and allow the system to initialise.
Confirm that:
- The display starts normally
- No critical warnings remain active
- The touchscreen or controls respond
- The system does not freeze
- The display does not repeatedly restart
- The expected machine profile loads
- Sensors begin communicating
- The GNSS receiver connects
- The project information appears reasonable
Do not repeatedly clear warning messages without recording or reporting them.
Recurring warnings may indicate a developing fault, even when the system continues operating.
6. Confirm the Correct Excavator Profile
Some machine control displays can store configurations for several machines.
Confirm that the active machine profile matches the excavator being operated.
The profile may contain:
- Boom measurements
- Stick measurements
- Machine-body dimensions
- GNSS antenna offsets
- Sensor configuration
- Quick-hitch geometry
- Attachment profiles
- Communication settings
Using a profile from another excavator can produce incorrect bucket guidance even when the hardware appears to work normally.
This check is particularly important after:
- A display replacement
- A software update
- A configuration restore
- A technician service
- Hardware transfer between machines
- Changes to the machine-control installation
7. Confirm the Correct Attachment Profile
Selecting the correct attachment is one of the most important excavator machine control checks.
The system uses stored attachment measurements to calculate the physical location of the cutting edge.
Common attachment profiles may include:
- General-purpose bucket
- Mud bucket
- Trenching bucket
- Rock bucket
- Batter bucket
- Tilt bucket
- Tiltrotator bucket
- Ripper
- Compaction wheel
- Grab
- Custom attachment
Before starting excavation:
- Identify the attachment physically fitted to the excavator.
- Confirm the matching attachment name on the display.
- Check the active quick-hitch configuration.
- Confirm that the bucket has not been modified.
- Check whether the cutting edge or teeth have changed.
- Complete the required accuracy check.
The correct attachment must also be selected every time the operator changes buckets or tools during the shift.
8. Inspect the Bucket and Cutting Edge
A correctly selected attachment profile may still be inaccurate if the physical bucket has changed since it was measured.
Inspect the attachment for:
- New cutting edges
- Worn cutting edges
- Replacement teeth
- Added wear plates
- Bucket repairs
- Structural modifications
- Changed pickup points
- Quick-hitch repairs
- Bent side plates
- Excessive pin or bush wear
Any change to the physical location of the guided point can affect the relationship between the bucket and the stored profile.
The bucket profile should be checked after:
- Cutting-edge replacement
- Bucket rebuilds
- Welding repairs
- Tooth-system changes
- Quick-hitch replacement
- Significant attachment wear
9. Confirm Sensor Communication
Review the system’s sensor-status screen.
Confirm that all required sensors are:
- Detected
- Communicating
- Producing reasonable values
- Updating continuously
- Free from active warning messages
A sensor communication problem may appear as:
- Frozen bucket movement
- Missing bucket guidance
- An unrealistic angle
- A warning symbol
- A disconnected-sensor message
- Sudden changes in displayed position
- Guidance that works in only part of the operating range
Intermittent sensor faults should be reported even when the sensor reconnects by itself.
10. Confirm GNSS Positioning
Check that the GNSS receiver is tracking satellites and producing a stable position.
The display may provide information such as:
- Number of tracked satellites
- Satellite constellation status
- Estimated position quality
- Antenna status
- Correction age
- Horizontal or vertical precision
- GNSS warnings
Multi-constellation GNSS receivers may track GPS, GLONASS, Galileo and BeiDou signals to improve satellite availability and positioning reliability.
GNSS reception may be affected by:
- Pit walls
- Buildings
- Bridges
- Stockpiles
- Dense vegetation
- Large machines
- Metal structures
- Restricted sky visibility
Operators should recognise that poor satellite visibility may affect performance even when the receiver and antennas are operating correctly.
11. Confirm RTK Fixed Status
Most 3D excavator machine control systems rely on RTK corrections to achieve centimetre-level positioning.
Corrections may be received through:
- A local RTK base station
- A site radio network
- A cellular modem
- A network RTK service
- An internet-based correction service
The display may show statuses such as:
- Autonomous
- DGPS
- Float
- RTK float
- Fixed
- RTK fixed
- Correction lost
Terminology varies between systems, so operators must understand which status is required on their site.
Fixed Does Not Confirm the Entire System Is Accurate
An RTK fixed status generally confirms the quality of the GNSS positioning solution.
It does not confirm that:
- The correct bucket is selected
- The bucket measurements are correct
- The sensors are calibrated
- The correct design is loaded
- The site localisation is correct
- The GNSS antenna has not moved
RTK is only one part of the complete machine-control accuracy chain.
Red Edge’s excavator solutions use RTK corrections to support centimetre-level machine positioning in demanding construction and mining environments.
Check RTK Stability
Do not begin precision excavation simply because the display briefly shows fixed status.
Confirm that the solution remains stable while the excavator moves.
Report situations where:
- RTK repeatedly changes between fixed and float
- The system takes longer than normal to reach fixed
- Position values jump
- Corrections drop when the house rotates
- The signal works in one area but not another
- Correction age becomes excessive
- The radio or mobile connection repeatedly disconnects
12. Confirm the Correct Project File
Check that the active digital design matches the work being completed.
Verify:
- Project name
- Work area
- Design surface
- Construction stage
- File date
- Revision number
- Alignment
- Relevant linework
- Superseded-file status
Different design revisions may look almost identical while containing different:
- Finished levels
- Batters
- Slopes
- Drainage lines
- Road alignments
- Construction stages
- Exclusion areas
Do not begin excavation when the design revision cannot be confirmed.
Contact the surveyor, engineer, supervisor or project data manager before proceeding.
13. Confirm the Coordinate System and Localisation
A machine can have a stable RTK fixed solution and still be incorrectly positioned relative to the project.
Confirm that:
- The excavator appears in the correct work area
- The machine moves in the correct direction on screen
- The design orientation matches the site
- Elevations appear reasonable
- The expected site localisation is active
- Easting and northing values appear appropriate
- The correct vertical datum is being used
Possible signs of a coordinate or localisation problem include:
- The machine appearing outside the project
- The design being rotated
- Unrealistic cut-and-fill values
- Large consistent height differences
- The horizontal position appearing correct while elevation is wrong
- The machine moving backwards or sideways on the display
- Design features not matching survey marks
Do not hide coordinate problems by applying an arbitrary vertical or horizontal offset.
The underlying configuration should be investigated.
14. Move the Excavator Through Its Working Range
Before beginning production, move the excavator slowly through a normal operating range.
Cycle:
- Boom
- Stick
- Bucket
- Tilt function
- Rotation function
- Quick hitch, where appropriate
Observe the display and confirm that:
- The digital bucket follows the physical bucket
- Values update smoothly
- Sensors remain connected
- Cables do not stretch or catch
- Bucket angle appears reasonable
- Tilt or rotation responds correctly
- RTK remains stable
- No new warnings appear
Intermittent faults may only become visible when the machine reaches a particular position.
15. Complete a Known-Point Check
A known-point check compares the machine control result with an established reference.
Depending on site procedures, the operator may:
- Place the bucket tip on a survey nail
- Touch a benchmark
- Use a designated machine-control check point
- Place the cutting edge on a calibration block
- Compare against a verified level
The check helps confirm:
- Correct machine profile
- Correct attachment profile
- Bucket-tip geometry
- Sensor calibration
- GNSS height
- RTK positioning
- Site localisation
Record the Result
Where required, record:
- Date
- Time
- Machine
- Operator
- Attachment
- Check point
- Expected value
- Displayed value
- Difference
- RTK status
- Action taken
If the result is outside the project tolerance, stop relying on machine guidance until the cause has been identified.
16. Confirm the Guidance Is Reasonable
Compare the displayed cut-and-fill information with visible site conditions and the expected work.
Ask:
- Does the displayed excavation depth make sense?
- Is the machine shown in the correct location?
- Does the surface match the current construction stage?
- Does the drainage grade fall in the expected direction?
- Are nearby levels consistent with known survey marks?
- Does the batter or trench alignment appear correct?
Warning signs include:
- Several metres of cut shown on a near-finished surface
- Fill displayed where excavation is expected
- A drainage line falling in the wrong direction
- The machine appearing outside the work zone
- Guidance values changing while the bucket is stationary
- Large differences from nearby survey marks
Technology should support operator and site knowledge, not replace practical judgement.
17. Review the Previous Shift Handover
Review previous operator notes and maintenance records for:
- RTK dropouts
- Sensor warnings
- Display restarts
- Incorrect levels
- Attachment changes
- Temporary repairs
- New project files
- Calibration concerns
- Technician attendance
- Areas with restricted GNSS reception
Machine-control faults can be intermittent.
The absence of a warning during the current pre-start does not necessarily mean the previous issue has been resolved.
Excavator Machine Control Stop-Work Conditions
Operators should stop relying on machine guidance when:
- The required RTK fixed status cannot be maintained
- A known-point check is outside tolerance
- The correct attachment profile cannot be confirmed
- The project revision cannot be verified
- The site localisation appears incorrect
- A GNSS antenna has moved
- A sensor is loose or damaged
- Position values jump unexpectedly
- Sensor communication repeatedly fails
- The displayed bucket does not follow the physical bucket
- Guidance conflicts significantly with survey control
- The operator cannot explain an abnormal value
The excavator may still be able to continue using an approved alternative method, such as laser guidance or traditional survey set-out.
However, the machine control system should not be treated as accurate until the problem has been investigated.
Common Excavator Machine Control Pre-Start Problems
RTK Is Fixed, but the Bucket Position Is Wrong
Possible causes include:
- Incorrect bucket profile
- Incorrect quick-hitch configuration
- Changed cutting edge
- Bucket repair
- Incorrect machine profile
- Sensor movement
- Calibration error
RTK fixed confirms the GNSS solution. It does not confirm bucket geometry.
One Bucket Is Accurate, but Another Is Not
This normally indicates an attachment-specific issue.
Check:
- Selected attachment
- Stored measurements
- Cutting edge
- Teeth
- Quick-hitch configuration
- Repairs or modifications
- Tilt or rotation setup
The Bucket Position Changes as the Machine Rotates
Possible causes include:
- Antenna offset error
- Loose GNSS antenna
- Machine-body sensor problem
- Incorrect heading configuration
- Unstable RTK
- Calibration error
Sensors Disconnect During Boom Movement
Possible causes include:
- Damaged cable
- Loose connector
- Cable stretching
- Pinched wiring
- Poor cable routing
- Sensor power issue
Inspect the wiring through the full range of movement.
The Machine Appears in the Wrong Location
Check:
- Project selection
- Coordinate system
- Site localisation
- GNSS receiver settings
- Design coordinates
- Easting and northing configuration
Cut-and-Fill Values Change While the Bucket Is Stationary
Possible causes include:
- Unstable GNSS
- RTK float status
- Loose antenna
- Moving sensor
- Electrical fault
- Signal reflection
- Incorrect localisation
Operator Checks Versus Technician Checks
| Operator Pre-Start Checks | Technician or Survey Support |
| Visual inspection | Full machine measurement verification |
| Correct machine profile | Sensor replacement |
| Correct attachment selection | Cable repairs |
| GNSS and RTK status | Receiver and radio configuration |
| Project revision check | Site localisation troubleshooting |
| Known-point check | Full recalibration |
| Basic connector inspection | Firmware and software management |
| Sensor-status review | Coordinate-system investigation |
| Recording faults | Hydraulic-control diagnosis |
| Reasonableness check | Internal component repair |
Operators should not change machine dimensions, calibration values or offsets unless they have been trained and authorised to complete the relevant procedure.
Printable Excavator Machine Control Pre-Start Record
| Field | Record |
| Date | |
| Project | |
| Machine identification | |
| Operator | |
| Design revision | |
| Attachment fitted | |
| Attachment profile selected | |
| Quick-hitch profile | |
| GNSS status | |
| RTK status | |
| Sensors communicating | Yes / No |
| Antennas secure | Yes / No |
| Wiring visually inspected | Yes / No |
| Known-point expected value | |
| Known-point displayed value | |
| Difference | |
| Within project tolerance | Yes / No |
| Faults identified | |
| Action taken | |
| Operator sign-off | |
| Supervisor sign-off |
This record can be incorporated into:
- Daily machine pre-starts
- Digital fleet forms
- Project quality documentation
- Equipment history
- Maintenance records
- Technical support reports
How Often Should Excavator Machine Control Be Professionally Checked?
Daily operator checks should be supported by planned technical inspections.
| Operating Environment | Suggested Check Interval |
| High-production mining excavator | Every 3–6 months |
| Major civil construction excavator | Every 3–6 months |
| General earthmoving excavator | Every 6–12 months |
| Low-use or backup machine | Annually or before a major project |
| After sensor or antenna movement | Before returning to guided work |
| After bucket repair or modification | Verify attachment measurements |
| After major machine repairs | Complete system inspection |
| After unexplained accuracy errors | Immediate technical assessment |
| Before mobilisation to a new site | Verify calibration, project data and RTK setup |
Professional checks may include system diagnostics, performance testing, calibration and preventative-maintenance recommendations.
Why Operator Training Matters
An excavator operator needs to understand more than how to follow cut-and-fill arrows.
Effective training should cover:
- System startup
- Machine-profile selection
- Attachment selection
- Quick-hitch configuration
- GNSS status
- Fixed versus float RTK
- Project-file selection
- Design revisions
- Site localisation
- Known-point checks
- Warning messages
- Stop-work conditions
- Fault reporting
- Basic equipment care
Red Edge supports contractor-installed machine guidance systems with setup, calibration and technical assistance, while also providing professional installation and training services.
Refresher training should be considered when:
- New operators join the business
- New attachments are introduced
- Software changes
- Hardware is upgraded
- Project procedures change
- Similar operator errors repeatedly occur
How Daily Checks Support Preventative Maintenance
A daily pre-start inspection does not replace professional preventative maintenance.
The two processes serve different purposes.
Daily operator checks help identify visible damage, incorrect settings and immediate faults.
Scheduled professional inspections can assess:
- Machine measurements
- Attachment geometry
- Sensor alignment
- Wiring integrity
- GNSS performance
- RTK communication
- Software and firmware
- Complete system calibration
- Accuracy across the working range
Red Edge Resources provides installation, preventative maintenance, training and ongoing technical support as part of its machine solutions offering.
Why Choose Red Edge Resources?
At Red Edge Resources, we believe reliable machine control depends on more than supplying hardware.
Our services include:
- Independent machine control advice
- Excavator system installation
- Machine measurement
- Bucket and attachment calibration
- GNSS configuration
- RTK setup
- Site commissioning
- Operator training
- Preventative maintenance
- Remote diagnostics
- Technical repairs
- Field support
- System upgrades
We work with contractors to ensure the selected system is correctly installed, accurately calibrated and supported throughout its operating life.
Contact Red Edge Resources to discuss excavator machine control installation, calibration, health checks or operator training. Red Edge lists service capability across Brisbane, Toowoomba, Rockhampton, Mackay, Moranbah and Perth.
Frequently Asked Questions
Should excavator machine control be checked every day?
Yes.
A daily inspection can identify incorrect attachments, moved sensors, damaged cables, unstable RTK corrections and project-data problems before they affect excavation.
Does RTK fixed mean the bucket is accurate?
No.
RTK fixed confirms the GNSS positioning solution. Bucket accuracy also depends on machine geometry, sensor calibration, attachment measurements, project data and site localisation.
Should the system be checked after changing buckets?
Yes.
Select the correct attachment profile and complete the required accuracy check before relying on the displayed cutting-edge position.
What should the operator do when the system is in RTK float?
Avoid precision machine-guided work and follow the site procedure.
Check satellite visibility, radio or cellular communication, antenna condition and correction status. Report persistent float conditions.
What happens when a known-point check fails?
Stop relying on machine guidance.
Check the machine profile, attachment profile, RTK status, project file and site localisation. Technician or survey support may be required.
Can an operator change bucket dimensions?
Only when trained and authorised.
Incorrect measurement changes can introduce additional errors and make future troubleshooting more difficult.
Can a new cutting edge affect machine-control accuracy?
Yes.
Replacing a cutting edge or teeth can change the physical point being guided. The attachment profile should be verified before accurate excavation continues.
Can poor RTK reception look like a calibration problem?
Yes.
Unstable corrections can cause the calculated position or elevation to fluctuate. Both the GNSS solution and machine calibration should be investigated.
Does the pre-start replace professional calibration?
No.
The pre-start confirms that the system appears ready for daily operation. Professional calibration verifies the relationship between the physical machine and the complete electronic guidance system.
Conclusion
An excavator machine control pre-start inspection is a simple but essential part of accurate digital excavation.
Before relying on guidance, operators should confirm:
- GNSS antennas are secure
- Sensors and brackets are undamaged
- Wiring is protected
- The correct excavator profile is active
- The correct bucket and quick hitch are selected
- Sensors are communicating
- GNSS positioning is stable
- RTK corrections are fixed
- The current project revision is loaded
- The correct localisation is active
- The bucket follows the display correctly
- The known-point check is within tolerance
- Cut-and-fill values are reasonable
These checks help prevent over-excavation, incorrect levels, rework, downtime and avoidable technical call-outs.
A machine control display should never be treated as accurate simply because it is producing guidance. Reliable results depend on the complete workflow—from GNSS and RTK corrections through to sensors, machine measurements, attachment profiles, digital designs and operator procedures.
At Red Edge Resources, we help Australian contractors build reliable machine control workflows through professional installation, commissioning, calibration, operator training, preventative maintenance and ongoing support.
Internal Links
Use these links naturally throughout the article:
- Excavator Machine Control Solutions
https://rededgeresources.com.au/excavator-solutions/ - STX-DIG Excavator Machine Control
https://rededgeresources.com.au/stx-dig-excavators/ - Stonex Machine Control Systems
https://rededgeresources.com.au/stonex-machine-control/ - Machine Control Services
https://rededgeresources.com.au/services/ - Machine Control Self-Installation Support
https://rededgeresources.com.au/how-contractors-can-successfully-install-their-own-machine-control-systems-with-red-edge-resources/ - Technical Repairs and Calibration
https://rededgeresources.com.au/technical-repairs/ - Stonex GNSS Receivers
https://rededgeresources.com.au/stonex-gnss-receivers/ - Red Edge Knowledge Base
https://rededgeresources.com.au/institute-login/ - Contact Red Edge Resources
https://rededgeresources.com.au/contact/
Machine Control Installation: Why Professional Commissioning
Protecting Accuracy, Reliability and Return on Investment from Day One
Installing a machine control system involves far more than mounting a display, connecting several sensors and switching on a GNSS receiver.
For the system to provide dependable guidance, every component must be correctly positioned, measured, configured, calibrated and tested as part of one integrated installation.
This process is known as commissioning.
Professional commissioning confirms that the physical machine, electronic sensors, GNSS equipment, RTK corrections, digital project data and in-cab display are all working together correctly.
When commissioning is completed properly, machine control can help contractors:
- Improve excavation and grading accuracy
- Reduce rework
- Reduce repetitive survey set-out
- Increase operator productivity
- Improve material control
- Reduce unnecessary passes
- Complete work closer to design
- Build operator confidence
- Protect the value of the technology investment
When installation or commissioning is incomplete, even high-quality machine control equipment can produce inconsistent or misleading guidance.
At Red Edge Resources, our machine control capability is built around practical installation, commissioning, calibration, training and field support across Australian civil and mining environments. Red Edge provides installation, preventative maintenance, hands-on training and ongoing technical support as part of its machine technology services.
What Is Machine Control Commissioning?
Machine control installation refers to fitting the hardware and connecting the system to the machine.
Commissioning is the broader process of confirming that the complete system is ready to perform accurately and reliably in the field.
A professional commissioning process may include:
- Inspecting the machine
- Confirming system compatibility
- Planning sensor and antenna locations
- Installing mounting brackets
- Routing and protecting wiring
- Measuring the machine
- Measuring attachments
- Configuring sensors
- Setting GNSS antenna offsets
- Connecting RTK corrections
- Loading machine profiles
- Configuring project files
- Completing system calibration
- Testing accuracy
- Verifying hydraulic control where applicable
- Training operators
- Recording the completed configuration
Installation puts the equipment on the machine.
Commissioning confirms that the equipment can be trusted.
Why Correct Installation Is Critical
Machine control calculates the position of a blade, bucket, drill or other working point using information gathered from several connected components.
Depending on the system, this may include:
- GNSS antennas
- GNSS receivers
- RTK radios or cellular modems
- Boom sensors
- Stick or dipper sensors
- Bucket sensors
- Blade sensors
- Pitch and roll sensors
- Inertial measurement units
- Hydraulic control modules
- Machine dimensions
- Attachment dimensions
- Digital design files
- Site coordinate systems
A small error in one component can affect the final guidance shown to the operator.
For example:
- An incorrect antenna offset can affect machine position.
- A poorly mounted sensor can move under vibration.
- An inaccurate bucket measurement can change the displayed cutting edge.
- Incorrect radio settings can interrupt RTK corrections.
- Poorly routed cables can fail as the machine articulates.
- An incorrect project coordinate system can place the machine away from the design.
- Incomplete hydraulic calibration can produce unstable automatic control.
Professional installation addresses the complete system rather than treating each component in isolation.
Installation Versus Commissioning
| Installation | Professional Commissioning |
|---|---|
| Hardware is fitted to the machine | The complete system is tested as an integrated solution |
| Sensors and antennas are mounted | Sensor positions and offsets are verified |
| Cables are connected | Cable routing and communication are tested through the machine’s operating range |
| Display is powered on | Machine and attachment profiles are configured |
| GNSS receiver is connected | RTK performance and site coordinates are checked |
| Machine measurements may be entered | Measurements are verified against the physical machine |
| System appears operational | Accuracy is checked against a known reference |
| Basic handover may occur | Operator workflow and fault recognition are covered |
| Limited documentation may be provided | Final settings, calibration and test results are recorded |
A system can be technically installed without being correctly commissioned.
This is one of the main reasons a newly fitted machine control system may appear to work but fail to deliver consistent results.
What Professional Machine Control Installation Should Include
1. Machine and Application Assessment
Before installation begins, the supplier should understand:
- Machine make
- Machine model
- Machine year
- Machine size
- Machine configuration
- Attachment types
- Hydraulic capability
- Electrical system
- Intended projects
- Accuracy requirements
- Operator workflow
- RTK correction source
- Existing survey or GNSS equipment
The system should be selected and configured for the application rather than fitted as a generic package.
An excavator used for drainage and final trim may require a different setup from an excavator used primarily for bulk earthworks.
Similarly, a dozer using automatic blade control requires different integration from a basic indicate-only guidance system.
2. Pre-Installation Machine Inspection
The installer should inspect the machine before mounting equipment.
This helps identify:
- Damaged mounting areas
- Existing electrical faults
- Hydraulic leaks
- Poor cable pathways
- Attachment wear
- Structural modifications
- Access limitations
- Existing accessories
- Potential sensor interference
- Areas exposed to impact or excessive heat
Identifying these conditions early reduces the risk of installation problems and future component damage.
3. Sensor Placement
Sensors must be mounted where they can accurately measure machine movement while remaining protected from impact, vibration and environmental exposure.
Sensor placement should consider:
- Machine geometry
- Range of movement
- Bracket rigidity
- Cable access
- Service access
- Potential collision points
- Hydraulic hoses
- Heat sources
- Mud and material buildup
- Attachment changes
A sensor bracket that flexes or moves can introduce an error even when the sensor itself is working correctly.
Mounting hardware must therefore be designed and installed as part of the accuracy system.
4. GNSS Antenna Installation
GNSS antenna position is a critical part of 3D machine control.
The installer must consider:
- Clear view of the sky
- Machine orientation
- Antenna separation on dual-antenna systems
- Structural rigidity
- Protection from impact
- Safe machine access
- Cable routing
- Stored antenna offsets
- Ease of inspection
Antenna mounts must remain stable under normal machine vibration and operation.
Where antennas are removable, the system must also include a consistent process for reinstalling them in the correct position.
5. Wiring and Cable Protection
Poor wiring installation is one of the most common causes of ongoing machine control faults.
Machine control cables may be exposed to:
- Constant vibration
- Boom and blade movement
- Hydraulic hose movement
- Heat
- Dust
- Water
- Hydraulic oil
- Abrasion
- Pinching
- Pressure washing
Professional cable routing should include:
- Appropriate conduit
- Secure mounting
- Strain relief
- Protected connectors
- Safe bend radius
- Separation from heat sources
- Clearance from articulation points
- Service loops where required
- Access for future maintenance
The installer should move the machine through its operating range and confirm that cables do not stretch, rub, catch or become pinched.
6. Power Supply and Electrical Integration
A stable power supply is essential for displays, receivers, sensors, radios and control modules.
Electrical installation may include:
- Correct voltage supply
- Fuse protection
- Ground connection
- Ignition switching
- Relay control
- Battery isolation compatibility
- Surge protection
- Connector sealing
- Power consumption assessment
An unstable electrical supply can cause:
- Unexpected display restarts
- Communication faults
- Sensor dropouts
- Receiver resets
- Data loss
- Intermittent system behaviour
Electrical testing should therefore form part of commissioning.
Accurate Machine Measurements
Machine control systems calculate the working point using stored machine dimensions.
These may include:
- Boom length
- Stick or dipper length
- Bucket dimensions
- Blade dimensions
- Pivot locations
- GNSS antenna offsets
- Machine-body offsets
- Sensor positions
- Quick-hitch measurements
- Tilt or rotation geometry
These measurements must accurately represent the physical machine.
Even small measurement errors can become more significant when calculated through several moving machine components.
Red Edge describes its machine-control setup process as including machine measurement, sensor configuration and calibration checks rather than relying on hardware installation alone.
Attachment Measurement and Calibration
Attachment profiles are especially important on excavators.
A machine may use:
- General-purpose buckets
- Mud buckets
- Trenching buckets
- Rock buckets
- Rippers
- Tilt buckets
- Rotating hitches
- Compaction wheels
- Grabs
- Specialist attachments
Each attachment may have different:
- Length
- Width
- Cutting-edge position
- Pin location
- Hitch geometry
- Tilt offset
- Rotation offset
Incorrect attachment measurements can cause the display to indicate that the bucket is on grade when the physical cutting edge is too high or too low.
Professional commissioning should include:
- Clear attachment identification
- Accurate physical measurement
- Correct profile setup
- Cutting-edge definition
- Tilt or rotation configuration
- Operator selection process
- Accuracy verification
Attachment profiles should also be documented so they can be checked after repairs or modification.
GNSS and RTK Commissioning
A 3D machine control system normally depends on RTK corrections to achieve the positioning accuracy required for detailed construction work.
The correction source may include:
- Local RTK base station
- Site radio network
- Network RTK service
- Cellular corrections
- Internet-based correction service
Commissioning should confirm:
- Receiver configuration
- Correction format
- Radio frequency
- Radio channel
- Cellular connection
- SIM and data settings
- Antenna condition
- Base-station compatibility
- Coordinate reference system
- Correction age
- Fixed solution stability
It is not enough for the system to briefly display an RTK fixed status.
The correction must remain stable while the machine moves and works throughout the intended operating area.
Coordinate Systems and Site Localisation
One of the most serious commissioning risks is incorrect coordinate-system configuration.
A machine can have stable RTK positioning but still be wrong relative to the project design.
The commissioning process should verify:
- Horizontal coordinate system
- Vertical datum
- Geoid or elevation model
- Site localisation
- Control points
- Easting and northing orientation
- Project design position
- Machine position
- Known elevations
Warning signs of poor coordinate configuration include:
- Machine appearing away from the work area
- Correct horizontal position but incorrect height
- Rotated design
- Unexpected cut-and-fill values
- Design not matching survey marks
- Large constant vertical offsets
Coordinate problems should be corrected at the source rather than hidden using arbitrary offsets.
Digital Project File Setup
The machine control system must be configured to display and manage the digital data used on the project.
This may include:
- Surface models
- DXF linework
- LandXML files
- Alignments
- Points
- Drainage lines
- Road strings
- Design boundaries
- Exclusion zones
Professional commissioning should confirm:
- Supported file format
- Correct coordinate system
- Current design revision
- Surface integrity
- Linework visibility
- Layer structure
- File naming
- Project selection
- Revision control
- Data-transfer process
Red Edge-supported machine control systems can incorporate design-file integration and real-time cut-and-fill guidance using RTK GNSS positioning.
Machine Control Calibration
Calibration establishes the relationship between the physical machine and the electronic system.
Depending on the machine, calibration may include:
- Sensor zero positions
- Boom calibration
- Stick calibration
- Bucket calibration
- Blade calibration
- Pitch and roll calibration
- Machine-body alignment
- Antenna alignment
- Tilt calibration
- Rotation calibration
- Hydraulic response
- Valve timing
Calibration must be completed using the manufacturer’s required procedure and verified using an independent reference where possible.
A system should not be considered commissioned simply because the calibration software reports completion.
The result must be checked on the actual machine.
Accuracy Verification
The final stage of commissioning should confirm that the machine provides accurate guidance under realistic operating conditions.
This may involve:
- Known-point check
- Bucket-tip check
- Blade-height check
- Slope check
- Rotation check
- Multiple machine positions
- Different boom or blade positions
- Different attachments
- Comparison with survey control
- Repeated measurements
- RTK stability check
Accuracy should be tested through the machine’s normal working range.
For an excavator, this may include checking the bucket:
- Close to the machine
- At normal reach
- At extended reach
- At different bucket angles
- In different machine orientations
A system that is accurate in only one position has not been fully verified.
Hydraulic Commissioning
Automatic machine control systems may interface with the machine’s hydraulics.
This can add significant productivity benefits, but it also makes commissioning more complex.
Hydraulic commissioning may include:
- Valve compatibility
- Control direction
- Minimum current
- Maximum current
- Valve deadband
- Hydraulic speed
- Sensor response
- Automatic mode activation
- Manual override
- Safety interlocks
- Emergency response
Poor hydraulic commissioning can result in:
- Oscillation
- Slow response
- Aggressive movement
- Overshooting grade
- Inconsistent control
- Operator discomfort
- Premature component wear
Automatic control should be tested under controlled conditions before production use.
Operator Training Is Part of Commissioning
The installation is not complete until operators understand how to use and check the system.
Commissioning training should cover:
- Starting the system
- Selecting the machine profile
- Selecting attachments
- Loading projects
- Understanding cut and fill
- Checking GNSS status
- Identifying RTK fixed and float
- Completing a known-point check
- Recognising warning messages
- Reporting faults
- Understanding stop-work conditions
- Protecting installed components
Operators should also understand what the system cannot confirm automatically.
For example, RTK fixed status does not confirm:
- Correct bucket profile
- Correct project revision
- Correct machine measurements
- Correct site localisation
- Correct calibration
Professional training helps operators use the system as an informed construction tool rather than blindly following the display.
Commissioning Documentation
A properly commissioned machine control system should have a documented configuration.
Records may include:
- Machine details
- System serial numbers
- Installed components
- Sensor locations
- GNSS antenna offsets
- Machine measurements
- Attachment measurements
- Calibration date
- Calibration results
- Software version
- Firmware version
- RTK configuration
- Radio settings
- Project settings
- Known-point results
- Operator training completed
- Outstanding recommendations
This documentation becomes valuable when:
- Troubleshooting faults
- Replacing components
- Recalibrating the machine
- Transferring hardware
- Adding attachments
- Completing warranty claims
- Reviewing system history
Risks of Poor Machine Control Installation
Inconsistent Accuracy
The machine may appear accurate in one position but show an error when the boom, bucket or blade moves.
Possible causes include:
- Incorrect machine measurements
- Flexible sensor brackets
- Poor calibration
- Incorrect offsets
- Loose antenna mounts
Frequent Communication Faults
Poor cable routing or connector protection can cause intermittent disconnections.
These faults may only occur when:
- The machine articulates
- The boom extends
- Hydraulic hoses move
- The machine vibrates
- Components become hot
Unstable RTK Performance
Incorrect radio or antenna installation can lead to:
- Short correction range
- Frequent float status
- Intermittent corrections
- Slow fixed solutions
- Dropouts in certain machine orientations
Operator Distrust
When guidance repeatedly disagrees with survey checks, operators may stop using the technology.
Once confidence is lost, even a repaired system may be underused.
Rework and Over-Excavation
Incorrect setup can result in:
- Digging below design
- Leaving excessive material
- Incorrect slopes
- Wrong trench depths
- Poor final trim
- Material replacement
- Additional survey attendance
Increased Downtime
An undocumented or poorly installed system is more difficult to diagnose.
Technicians may need to spend additional time identifying:
- Cable routes
- Unknown offsets
- Unlabelled components
- Incorrect profiles
- Unrecorded configuration changes
Professional Installation Versus Low-Cost Installation
| Key Area | Low-Cost or Incomplete Installation | Professional Commissioning |
|---|---|---|
| System selection | Based mainly on hardware price | Based on machine, application and workflow |
| Mounting | Generic component placement | Rigid, protected and machine-specific |
| Wiring | Basic connection | Protected routing tested through machine movement |
| Measurements | Entered quickly or estimated | Measured and independently checked |
| Attachments | One basic profile | Relevant attachments measured and verified |
| GNSS | Receiver connects | Antenna position, offsets and stability checked |
| RTK | Correction received | Fixed performance verified across work area |
| Project data | File loaded | Coordinates, revision and design checked |
| Calibration | Software procedure completed | Calibration independently verified |
| Operator handover | Basic button overview | Practical workflow and fault recognition |
| Documentation | Limited or absent | Complete configuration and test record |
| Support | Reactive assistance | Defined support and maintenance pathway |
The lowest installation price may not provide the lowest total cost.
Rework, downtime and repeated troubleshooting can quickly exceed the difference between a basic installation and professional commissioning.
Self-Installation Versus Professional Installation
Some machine guidance systems are designed to support contractor installation.
Self-installation may be suitable when:
- The system is designed for simplified installation
- The contractor has trained technical staff
- Machine measurements are clearly understood
- The mounting requirements are straightforward
- Remote commissioning support is available
- The contractor can complete accuracy verification
- The system does not require complex hydraulic integration
Red Edge supports self-installation pathways for suitable 1D, 2D and 3D machine guidance systems, including remote assistance, system setup and calibration support.
However, self-installation should not mean skipping commissioning.
Whether installed by a contractor or field technician, the system should still be:
- Correctly measured
- Properly configured
- Calibrated
- Accuracy tested
- Documented
- Supported by operator training
When Professional Installation Is Strongly Recommended
Professional commissioning is particularly important when:
- Installing full 3D machine control
- Integrating hydraulic automatic control
- Equipping a high-production machine
- Working on tight-tolerance projects
- Installing on a complex machine
- Using dual-GNSS antennas
- Integrating tiltrotators
- Adding multiple attachments
- Operating in remote mining environments
- Connecting to an existing RTK network
- Integrating survey equipment
- Standardising systems across a fleet
- Meeting client quality requirements
The greater the operational and financial risk, the stronger the case for professional commissioning.
Commissioning Different Machine Types
Excavator Machine Control
Excavator commissioning may include:
- Boom measurement
- Stick measurement
- Bucket and attachment profiles
- Quick-hitch setup
- Boom, stick and bucket sensor calibration
- Tilt or rotation setup
- GNSS antenna offsets
- Machine-body alignment
- Bucket-tip accuracy checks
Explore STX-DIG excavator machine control
Red Edge’s STX-DIG systems provide 3D guidance for excavators using GNSS positioning and digital designs to show the operator where to dig and grade.
Dozer Machine Control
Dozer commissioning may include:
- Blade geometry
- GNSS mast position
- Blade sensor calibration
- Cross-slope calibration
- Machine pitch and roll
- Hydraulic automatic-control tuning
- Blade-height verification
Grader Machine Control
Grader commissioning may involve:
- Mainfall sensor calibration
- Cross-slope calibration
- Blade rotation
- Hydraulic control
- GNSS mast alignment
- Design alignment
- Final-trim testing
Drill and Piling Systems
Commissioning may include:
- Mast alignment
- Pitch and roll
- GNSS antenna offsets
- Machine heading
- Drill or pile depth reference
- Design file setup
- Reporting configuration
- Position and alignment testing
What Happens After Commissioning?
Machine control installation should begin a long-term support relationship rather than end it.
After commissioning, the supplier should provide access to:
- Remote technical support
- Field servicing
- Calibration assistance
- Attachment setup
- RTK troubleshooting
- Software and firmware support
- Operator refresher training
- Preventative maintenance
- Replacement parts
- System upgrades
Red Edge Resources provides field and remote support across multiple Australian locations, including Brisbane, Rockhampton, Mackay, Moranbah and Perth.
Preventative Maintenance Protects Commissioning Accuracy
Even a correctly commissioned system requires ongoing checks.
Machine-control accuracy may change due to:
- Sensor movement
- Antenna movement
- Bracket damage
- Pin and bush wear
- Attachment repairs
- Cutting-edge replacement
- Wiring damage
- Machine repairs
- Software changes
- Hydraulic work
Daily operator checks and scheduled professional maintenance help preserve the original commissioning quality.
Related article:
Preventative Maintenance for Machine Control Systems
Questions to Ask a Machine Control Installer
Before approving an installation, ask:
- Is the system suitable for the machine and application?
- Who will measure the machine?
- Which attachments are included?
- How will the sensors be mounted?
- How will cables be protected?
- Is RTK configuration included?
- Is project-file setup included?
- Is site localisation included?
- Will accuracy be checked against a known point?
- Is hydraulic commissioning included?
- Is operator training included?
- Will commissioning results be documented?
- What warranty applies?
- Are spare parts available locally?
- What remote and field support is available?
- Who completes future calibration?
- What happens after bucket or machine repairs?
- Are travel and mobilisation included in the quote?
A complete quote should clearly distinguish between hardware supply, installation, commissioning, training and ongoing support.
Machine Control Commissioning Checklist
| Commissioning Area | Required Outcome |
|---|---|
| Machine assessment | System confirmed suitable for machine and application |
| Physical installation | Sensors, antennas and displays securely mounted |
| Wiring | Protected and tested throughout machine movement |
| Power supply | Stable and correctly fused |
| Machine measurements | Physically measured and verified |
| Attachment profiles | Correctly measured, named and tested |
| GNSS | Receiver and antennas correctly configured |
| RTK | Stable fixed solution confirmed |
| Coordinate system | Correct horizontal and vertical reference |
| Project files | Current design loaded and verified |
| Sensor calibration | Completed according to required procedure |
| Hydraulic control | Tuned and safely tested where fitted |
| Accuracy check | Verified against known control |
| Operator training | Daily workflow and fault recognition understood |
| Documentation | Final configuration and results recorded |
| Support pathway | Technical contacts and service process supplied |
Why Choose Red Edge Resources?
At Red Edge Resources, machine control installation is approached as a complete operational solution.
Our services include:
- Independent system selection
- Machine inspections
- Professional installation
- Machine measurement
- Attachment measurement
- Sensor configuration
- GNSS setup
- RTK commissioning
- Calibration
- Accuracy verification
- Hydraulic integration
- Operator training
- Remote support
- Field service
- Preventative maintenance
- Fleet technology reviews
Our capability is based on practical experience deploying machine control, surveying and communications technology in demanding Australian civil and mining environments.
We focus on selecting the right solution, installing it correctly and supporting the system throughout its working life.
Frequently Asked Questions
What is machine control commissioning?
Machine control commissioning is the process of configuring, calibrating, testing and verifying the complete installed system.
It confirms that the machine, sensors, GNSS receiver, RTK corrections, attachments and project data work together correctly.
Is commissioning different from installation?
Yes.
Installation fits and connects the hardware. Commissioning confirms that the complete system is accurate, reliable and ready for production.
How long does machine control installation take?
The installation period depends on:
- Machine type
- System complexity
- Number of sensors
- Attachment setup
- Hydraulic integration
- Machine condition
- RTK configuration
- Testing requirements
A simplified guidance system may be completed relatively quickly, while complex hydraulic or specialist installations may require additional setup and testing.
Does every attachment need to be measured?
Each attachment used for machine-guided work should have an accurate profile.
Attachments with different dimensions or cutting edges cannot safely share one generic profile.
Does RTK fixed confirm the system is calibrated?
No.
RTK fixed confirms the GNSS positioning solution. It does not confirm correct machine dimensions, attachment selection, sensor calibration, project data or localisation.
Can machine control be self-installed?
Some systems can be self-installed where the contractor has suitable technical capability and commissioning support.
The system must still be measured, calibrated and accuracy tested before production use.
Should the operator be present during commissioning?
Where possible, yes.
Operator involvement allows practical training to occur on the actual machine and helps establish the correct pre-start, project-selection and fault-reporting process.
What should be checked after installation?
The system should be checked for:
- Stable power
- Sensor communication
- Secure hardware
- Correct machine measurements
- Correct attachment profiles
- Stable RTK
- Correct project coordinates
- Accurate bucket or blade position
- Smooth hydraulic response where applicable
When is recommissioning required?
A complete or partial recommissioning may be required after:
- Sensor replacement
- Antenna movement
- Bracket repair
- Machine structural repairs
- Hydraulic changes
- Major software changes
- Hardware transfer
- Significant attachment modification
- Persistent accuracy problems
Conclusion
Machine control installation is not complete when the hardware is attached and the display powers on.
Reliable machine guidance depends on the complete system being:
- Correctly selected
- Securely installed
- Accurately measured
- Properly configured
- Connected to stable RTK corrections
- Calibrated
- Tested against known control
- Understood by the operator
- Documented for future support
Professional commissioning protects the contractor from many of the most common causes of machine-control underperformance, including incorrect measurements, poor sensor placement, unstable RTK, wiring faults, attachment errors and coordinate-system problems.
The result is not simply a cleaner installation.
It is a system that operators can trust, technicians can support and the business can use to improve productivity, accuracy and project delivery.
At Red Edge Resources, we provide professional installation, commissioning, calibration, training and ongoing support for machine control systems used throughout Australian civil, construction and mining operations.
Internal Links
Use these links naturally throughout the article:
- Machine Control Solutions
https://rededgeresources.com.au/machine-control/ - Red Edge Services
https://rededgeresources.com.au/services/ - STX-DIG Excavator Machine Control
https://rededgeresources.com.au/stx-dig-excavators/ - Machine Control Self-Installation Support
https://rededgeresources.com.au/how-contractors-can-successfully-install-their-own-machine-control-systems-with-red-edge-resources/ - Machine Control Systems for Excavators
https://rededgeresources.com.au/achieving-cost-savings-with-red-edges-machine-control-systems-for-excavators/ - Daily Machine Control Checks Every Operator Should Complete
https://rededgeresources.com.au/daily-machine-control-checks/ - Excavator Machine Control Pre-Start Inspection
https://rededgeresources.com.au/excavator-machine-control-pre-start-inspection/ - Preventative Maintenance for Machine Control Systems
https://rededgeresources.com.au/preventative-maintenance-machine-control-systems/ - Choosing the Right Machine Control System for Your Fleet
https://rededgeresources.com.au/choosing-the-right-machine-control-system-for-your-fleet/ - Contact Red Edge Resources
https://rededgeresources.com.au/contact/