Stonex Calibration and Commissioning

Two different milestones
Installation means the hardware is fitted. Commissioning means the system produces accurate output. They are not the same day’s work, and conflating them is how contractors end up with a system that is technically installed and practically unusable.
Machine calibration
The system needs to know the machine’s actual geometry — not the nominal dimensions from a brochure, but the real measurements of the machine in front of it.
Machine dimensions. Boom, stick and mounting point measurements, taken accurately.
Attachment geometry. Every bucket or blade in regular use, measured and entered.
Sensor positions. Where each sensor sits relative to the geometry.
Antenna positions. Where the antennas sit relative to the machine, and their separation.
Errors here propagate into everything the system produces. A dimension entered 20mm out means every measurement is 20mm out, consistently, with no error indication.
The attachment library
The most valuable hour of commissioning, and the most commonly skipped.
Every bucket and attachment in regular use should be measured and configured during commissioning — not on the day it is first needed on a job, by whoever is available, under time pressure.
Wrong attachment selection is the leading cause of “this system is inaccurate” complaints across every brand of machine control. Building a complete, correct attachment library up front eliminates most of them, and building attachment selection into the pre-start routine eliminates the rest.
Sensor calibration
Sensors are calibrated so their readings correspond correctly to actual machine geometry, typically by moving the machine through known positions and letting the system establish the relationships.
Stonex notes calibration is quick, with password-protected settings — worth using, because settings that anyone can change are settings that get changed. \[MFR]
Verification — the step that matters
Calibration is not complete until it has been verified against something independent.
Machine positioned at a known point or against a known surface
System reading compared against the known value
Tested at several positions across the working range, not just one
Result within tolerance, and recorded
Only then is the system released for production work
Testing at one position is not verification. Errors in geometry frequently show at the extremes of the working range while looking fine in the middle.
Site calibration, if 3D
For 3D configurations, machine calibration is only half of it. Site calibration ties GNSS positioning to your site coordinate system.
This is the highest-consequence setup task in the whole system, because a bad site calibration produces confident, precise, consistently wrong work with no error indication at all. It has its own article and its own verification process.
Ongoing verification
Commissioning establishes accuracy. Keeping it requires routine:
Pre-start known-point check. Fast, and it catches most problems before they become rework. Defined tolerance, recorded result, stated action on failure.
Recalibration after events. Component replacement, repair, significant impact, or any work on the machine geometry.
Periodic verification at a defined interval regardless of whether anything has happened.
Without this, crews either keep checking manually — losing the benefit while keeping the exposure — or stop checking entirely, which is worse.
Why this connects to everything else
The entire value case for machine control rests on people trusting the system enough to stop verifying manually.
They only trust it if it is right. It is only right if it is properly calibrated and routinely verified. A system commissioned in a hurry produces a site that never quite trusts it, and a site that never quite trusts it keeps every cost and every exposure it was meant to remove.
Red Edge provides calibration as part of Stonex installation and support. It is worth confirming what standard of verification is performed and what documentation you receive.
CTA: Ask Red Edge Resources what verification standard is applied at commissioning and what record you get.