Installing a Stonex Machine Control System
The question that gets asked first
Every plant manager asks the same thing: how long is my machine off the job?
Stonex’s own guidance is that a quick demonstration installation typically takes two to four hours, while a full professional setup may require up to a working day — six to eight hours. \[MFR]\[VERIFY] — confirm this against Red Edge’s actual experience on Australian machines. Manufacturer figures are usually derived under favourable conditions on common machine types; a real figure from your technicians, stated honestly, is more useful and more credible than a manufacturer optimum.
Either way, plan it into a period when the machine is not on the critical path. Downtime costed at your plant rate is a genuine line item that never appears on a quote.
What gets fitted
Angle sensors on the machine geometry — boom (single or dual), stick, bucket and frame for an excavator; on the blade for a dozer.
GNSS antennas, where the configuration includes them. Cab roof for excavators; for wheel loaders, either the rear frame or the front frame depending on machine design.
The receiver, where fitted.
The display and its mount.
Connection box, cabling and looms.
What separates a good install
The hardware is the same regardless of who fits it. Installation quality is what determines whether the system is still working in two years.
Sensor mounting. Earthmoving machines destroy poorly mounted equipment. Mounts need to be secure, correctly positioned and protected from strikes. A sensor that shifts on its mount produces errors that are difficult to diagnose, because nothing has obviously failed.
Cable routing. Cables need to be routed away from pinch points, heat, and anywhere they will chafe against moving components. Poor routing is the single most common cause of intermittent faults, and intermittent faults are the most expensive kind to chase.
Connector protection. Connectors are where dust and moisture get in. Sealing and positioning matter.
Display position. Visible at a glance without competing with the operator’s view of the work. This is a decision made at fit-out and lived with for years — worth getting right rather than accepting wherever the bracket happened to fit.
Antenna geometry. Where two antennas provide heading, the separation between them affects precision. Follow the specified geometry rather than mounting them where it is convenient.
Machine compatibility
Stonex states installation across a wide range of excavator brands, models and sizes. \[MFR]
Worth confirming specifically for your machines rather than relying on the general statement — particularly for older machines, unusual configurations, or anything with non-standard boom arrangements. Articulated and two-piece booms in particular are a question worth asking directly.
Warranty
Confirm with your machine manufacturer or dealer what aftermarket fitment means for your specific machine and warranty position. This varies by manufacturer and it is worth getting in writing rather than assuming in either direction.
Downtime planning
Schedule around work. Fit during planned maintenance, between jobs, or in a lull.
Don’t do the whole fleet at once. Something will not go smoothly, and you want capacity elsewhere when it does.
Allow for commissioning. Installation is not the end. Configuration, calibration and verification follow, and they take time.
Train close to use. Training delivered weeks before the machine goes into guided production is training that has to be repeated.
Who does it
Red Edge provides Stonex installation, calibration, operator training and technical support.\[VERIFY] — Red Edge’s live dozer page describes certified technicians using fully-equipped mobile service vehicles throughout Australia. If that is accurate and substantiable, it is a strong point worth making consistently across the site. Confirm before repeating it. Coverage claims are the ones a competitor complaint targets first.