Stonex Calibration and Commissioning

Two different milestones
Installation means the hardware is fitted. Commissioning means the system produces accurate output. They are not the same day’s work, and conflating them is how contractors end up with a system that is technically installed and practically unusable.
Machine calibration
The system needs to know the machine’s actual geometry — not the nominal dimensions from a brochure, but the real measurements of the machine in front of it.
Machine dimensions. Boom, stick and mounting point measurements, taken accurately.
Attachment geometry. Every bucket or blade in regular use, measured and entered.
Sensor positions. Where each sensor sits relative to the geometry.
Antenna positions. Where the antennas sit relative to the machine, and their separation.
Errors here propagate into everything the system produces. A dimension entered 20mm out means every measurement is 20mm out, consistently, with no error indication.
The attachment library
The most valuable hour of commissioning, and the most commonly skipped.
Every bucket and attachment in regular use should be measured and configured during commissioning — not on the day it is first needed on a job, by whoever is available, under time pressure.
Wrong attachment selection is the leading cause of “this system is inaccurate” complaints across every brand of machine control. Building a complete, correct attachment library up front eliminates most of them, and building attachment selection into the pre-start routine eliminates the rest.
Sensor calibration
Sensors are calibrated so their readings correspond correctly to actual machine geometry, typically by moving the machine through known positions and letting the system establish the relationships.
Stonex notes calibration is quick, with password-protected settings — worth using, because settings that anyone can change are settings that get changed. \[MFR]
Verification — the step that matters
Calibration is not complete until it has been verified against something independent.
Machine positioned at a known point or against a known surface
System reading compared against the known value
Tested at several positions across the working range, not just one
Result within tolerance, and recorded
Only then is the system released for production work
Testing at one position is not verification. Errors in geometry frequently show at the extremes of the working range while looking fine in the middle.
Site calibration, if 3D
For 3D configurations, machine calibration is only half of it. Site calibration ties GNSS positioning to your site coordinate system.
This is the highest-consequence setup task in the whole system, because a bad site calibration produces confident, precise, consistently wrong work with no error indication at all. It has its own article and its own verification process.
Ongoing verification
Commissioning establishes accuracy. Keeping it requires routine:
Pre-start known-point check. Fast, and it catches most problems before they become rework. Defined tolerance, recorded result, stated action on failure.
Recalibration after events. Component replacement, repair, significant impact, or any work on the machine geometry.
Periodic verification at a defined interval regardless of whether anything has happened.
Without this, crews either keep checking manually — losing the benefit while keeping the exposure — or stop checking entirely, which is worse.
Why this connects to everything else
The entire value case for machine control rests on people trusting the system enough to stop verifying manually.
They only trust it if it is right. It is only right if it is properly calibrated and routinely verified. A system commissioned in a hurry produces a site that never quite trusts it, and a site that never quite trusts it keeps every cost and every exposure it was meant to remove.
Red Edge provides calibration as part of Stonex installation and support. It is worth confirming what standard of verification is performed and what documentation you receive.
CTA: Ask Red Edge Resources what verification standard is applied at commissioning and what record you get.

Base Station Enclosure Specification Checklist

Most enclosure problems are specification problems, and they’re visible in the original enquiry if you know what to look for. “Need a box for a base station, roughly 600 wide” produces a box that’s roughly right, and roughly right is the expensive outcome.
Here’s what a fabricator actually needs to get it right the first time.

  1. The equipment schedule
    Every item going inside, with dimensions and mounting method.
    Make and model of each device
    Length × width × height for each, including connectors and any protruding cable strain relief
    How each one mounts — DIN rail, panel screws, brackets, free-standing
    Which ones need front access, and which need to be visible
    The item people forget is the one that gets added later. Include the thing that’s “probably going in next year”, because the marginal cost of allowing space now is close to zero and the cost of not having it is a second enclosure.
  2. The cable schedule
    Every cable entering or leaving, with:
    What it is — antenna feeder, DC supply, solar input, ethernet, serial
    Outside diameter, measured
    Which face of the enclosure it should enter
    Whether it’s a gland or a bulkhead connector (antenna feeder should be a bulkhead)
    This is the single highest-value item on the list, because entries fabricated in a workshop are neat and entries drilled on site rarely are.
  3. Where it’s going
    Specifically:
    Indoors or outdoors
    If indoors — container, shed, workshop, plant room, switchroom
    If outdoors — is there overhead cover, or is it fully exposed?
    Dust environment: office-clean, general site, or active dust source nearby
    Coastal, wash-down or chemical exposure
    Ambient temperature range
    The undercover-versus-exposed answer determines whether a ventilated enclosure is viable at all. Everything else is detail by comparison.
  4. Thermal load
    The continuous power dissipation of the equipment inside, in watts, is what determines whether ventilation is adequate.
    If you don’t have that number, list the devices and their continuous current draw and supply voltage. A transmitting radio in particular changes the picture, so state whether it’s transmitting continuously and at what output power.
  5. Mounting and access
    Floor-standing on a stand, wall-mounted, or fixed to a frame
    Available floor area and height clearance
    Which side the door needs to hinge, and how much swing room exists
    Whether the assembly needs to be bolted down, and to what — steel floor, concrete plinth, container deck
    Height at which the equipment needs to sit for operation and service
    Door swing is the detail that gets discovered on install day. Measure it.
  6. Power and battery
    Supply type: mains, genset, solar, or a combination
    Battery chemistry, capacity and physical dimensions
    Whether the battery mounts inside the enclosure, below it, or separately
    Whether DC distribution and protection are in scope
    The standard stand carries a 12 V battery mount, 500 × 190 × 45 mm, below the box. Anything outside that envelope — a larger battery, or more than one — needs to be raised at enquiry stage, because it affects the stand design.
  7. Finish and identification
    Natural aluminium, or powder coated / painted to a colour (specify the code)
    Any labelling, asset tagging or signage required
    Client or site standards that apply
  8. Scope of supply
    Be explicit about which of these you’re buying:
    Empty enclosure — box and stand, built to order, nothing inside
    Enclosure with internal fit-out hardware — backing panel, DIN rail, glands, fan, but no equipment
    Fitted unit — wired, with harness, DC distribution and protection, tested, ready for equipment or supplied with it
    These are materially different products at materially different prices, and the ambiguity between them is the most common source of disappointment. The Red Edge standard supply is the empty box and stand. A fitted unit is quoted separately once the internal scope is agreed.
  9. Commercial
    Delivery address and whether a tailgate or forklift is available
    Required delivery date, and whether it’s firm or indicative
    Whether the enclosure needs to arrive before or after the equipment it houses
    A note on what not to specify
    Don’t copy an IP rating from a previous document. Establish the environment and let the ingress strategy follow from it. Specifying IP66 for a container installation adds cost and creates a thermal problem, and specifying no rating for an exposed outdoor position creates a different and worse problem.
    Don’t specify dimensions before the equipment schedule. The box size is an output of what goes in it, not an input. An enquiry that leads with external dimensions usually means someone has measured a gap on site, which is useful information but not the same thing.
    Don’t leave the fit-out ambiguous. Write down which of the three scopes above you want.
    What happens next
    Send us the equipment schedule and the cable list and we’ll come back with a proposed configuration and dimensions. If it fits the standard 900 × 600 × 300 box, that’s the quickest and cheapest answer. If it doesn’t, we build non-standard sizes as normal work.
    We fabricate in our own Brisbane workshop, so changes to the design during the quoting stage are a conversation rather than a change order.
    CTA: Send your equipment and cable schedule to [email protected], or call 1300 769 359 to talk it through.

Custom vs Off-the-Shelf Equipment Enclosures: How to Decide

We fabricate enclosures to order in our own Brisbane workshop. That’s a reason to take the following with the appropriate scepticism — and also a reason it’s worth saying plainly that a catalogue enclosure is often the correct choice.
The decision comes down to a handful of factors, and most of the time it’s obvious once they’re written down.
When an off-the-shelf enclosure is the right answer
The equipment fits a standard size with room to spare. If what you’re housing sits comfortably inside a catalogue envelope, buying the catalogue box is faster and cheaper. There’s no engineering value in fabricating something that already exists.
You need it this week. A stocked enclosure ships immediately. A fabricated one has a lead time, because someone has to cut, weld, drill and finish it.
You need a specific IP rating. Ingress protection ratings are established by testing to a standard. A manufacturer producing a volume line has tested and certified their design. A one-off fabricated box has not been through that testing, and shouldn’t be represented as though it has. If your specification genuinely requires a rated enclosure, buy a rated enclosure.
You need many identical units. Volume manufacturing beats fabrication on cost at quantity. The crossover point is lower than most people assume.
Standard accessories matter. Catalogue enclosures come with a supporting ecosystem — gland plates, mounting kits, rails, doors, thermal accessories — that all fit. A custom box needs each of those solved individually.
When a built-to-order enclosure is the right answer
The equipment doesn’t fit anything standard. This is the most common driver. A GNSS receiver, a UHF radio, a charge controller and a DC distribution panel is an awkward combination, and the catalogue enclosure that fits it is either much too big or slightly too small in one dimension. Slightly too small is the killer.
The mounting arrangement is unusual. A stand with an integrated battery mount below the box, at a specific overall height, with feet drilled for plinth fixing, isn’t a catalogue item. Neither is a wall-mount variant of the same box for a plant room with no floor space.
You need penetrations in specific places. Drilling and glanding a catalogue enclosure on site is common and usually ends up messier than doing it in a workshop. If the cable schedule is known, having the entries fabricated in the right positions and correctly sized is a materially better outcome.
It has to match something. Existing site equipment, a client’s colour standard, a rack that’s already installed, a footprint someone else has already poured a plinth for.
The quantity is small and the specification is specific. One to twenty units with a defined requirement is squarely fabrication territory.
You want it wired. A fabricated enclosure can be supplied fitted out — backing panel, DIN rail, harness, DC distribution, glands — as a single item that arrives ready to commission. Buying a bare catalogue box and having an electrical contractor fit it out on site is a second procurement and a second set of site hours.
Cost, honestly
For a single unit with an unusual requirement, fabrication is often comparable to or cheaper than a catalogue enclosure of a similar size and quality, because you’re not paying for the volume manufacturer’s certification, distribution and accessory ecosystem.
For a single unit that fits a standard size, the catalogue box wins clearly.
For twenty identical units, the catalogue box usually wins unless the requirement is genuinely non-standard.
The costs that don’t appear in either quote are the ones worth attention: site labour to modify a box that nearly fits, a second mobilisation because the enclosure arrived without the entries in the right places, and the cost of the install being redone because the box was the wrong choice.
What we actually build
The Red Edge base station enclosure is 3 mm aluminium, TIG welded throughout, 900 H × 600 W × 300 D mm externally, with a full-height hinged door, an expanded aluminium mesh vent panel, a cut-out for a cooling fan and a natural aluminium finish. It’s supplied on a matching braced stand, 950 mm high, painted black, with a 12 V battery mount below the box.
It is a ventilated enclosure. It is not IP-rated, and we don’t recommend exposed outdoor mounting without additional weather protection. That’s the one specification point that most often determines whether we’re the right supplier for a given job.
Options include powder coat or paint to your colour, a cooling fan fitted with or without a thermostat, an internal backing panel and DIN rail, braided harness and DC distribution built in-house, cable glands and antenna lead-throughs, a wall-mount version without the stand, and non-standard sizes.
Standard supply is the box and stand, built to order, empty. A fitted unit is quoted as a separate line once the internal scope is agreed.
The question to ask first
Before comparing suppliers, answer this: is the enclosure going somewhere undercover, or somewhere exposed?
Undercover means a ventilated enclosure is viable, which opens up both catalogue and fabricated options at reasonable cost. Exposed means you need a sealed, rated enclosure with a thermal management strategy, which is a narrower and more expensive market, and one where the certification behind a catalogue product has real value.
Getting that answer wrong is more expensive than getting the custom-versus-catalogue decision wrong.
CTA: Tell us what needs to fit inside and we’ll size it. Built to order in Brisbane. Call 1300 769 359 or email [email protected].

Securing a Site GNSS Base Station

When a base station goes down and it isn’t a fault, the cause is usually one of three things. Someone took the battery. Someone unplugged something. Or someone opened the box, saw a flashing light, and switched it off to be helpful.
The third one is the most common and the least talked about, and it’s the reason a lockable enclosure earns its cost even on a site where theft isn’t a concern.
The three risks, in order of likelihood
Well-meaning interference. A base station is unattended equipment with lights on it. On a busy site, that attracts curiosity. An electrician looking for a 12 V source finds an unlocked box with a battery in it. A night shift supervisor sees an alarm LED and cycles the power. A cleaner unplugs something to run a vacuum. None of these people are doing anything wrong by their own lights, and all of them can take a base offline.
Opportunistic borrowing. A deep cycle battery is a universally useful item on a construction site. So is a length of heavy DC cable. Equipment that isn’t obviously someone’s, and isn’t locked, gets absorbed into general site stock.
Actual theft. GNSS receivers are valuable, portable and easy to move. Remote sites with limited surveillance are targets, and rural and regional sites in particular have seen sustained interest in survey and machine control equipment.
The controls that address the first two are cheap. The control that addresses the third is layered.
Layer one: the enclosure itself
The base station enclosure has a full-height hinged door with a hasp for padlocking. It’s a simple thing, and it does most of the work:
It stops casual opening entirely
It makes any interference deliberate rather than accidental
It creates an obvious ownership signal — locked equipment belongs to someone
It means the battery, sitting on the stand below the box, can be locked away as part of the same assembly
Choose the padlock deliberately. A shrouded or closed-shackle padlock resists bolt cutters far better than a standard shackle. Weatherproof it if the enclosure is in a damp area, because a seized padlock at 5 am causes its own problems.
Keyed-alike across a site’s enclosures is worth setting up — one key for the survey team, rather than a keyring nobody can identify.
Layer two: fixing it down
An enclosure that can be picked up and carried away isn’t secure regardless of the lock.
The stand feet are drilled for floor or plinth fixing. Bolting the assembly to a container floor or a concrete plinth means removing it requires tools and time, which is enough to deter most opportunistic removal.
Use tamper-resistant fasteners if the risk profile warrants it, and bolt through with backing washers rather than into a thin panel.
Layer three: siting
Where the base sits affects its security as much as how it’s locked.
Inside the compound, not at the edge. A base station in the middle of a fenced compound, overlooked by the site office, is a much harder target than one on the perimeter near a gate.
Visible from a work area. Equipment that people walk past regularly gets noticed when something’s wrong with it.
Not in the quietest corner. The instinct is to put the base somewhere out of the way. That’s the same place a thief would choose.
The tension here is real, because antenna siting wants a clear sky view, which often means an exposed position. The antenna can be exposed while the enclosure is not — that’s the point of running feeder. Put the antenna where the sky is and the box where the people are.
Layer four: knowing when something’s wrong
The fastest security control is noticing. A base station that reports its own state — battery voltage, correction output, uptime — tells you something has happened within minutes rather than when a crew arrives and can’t get a fix.
A battery monitor or shunt inside the enclosure gives a local view. Remote monitoring gives you the alert. Which of those you need depends on how far the site is from anyone who could respond.
Serial numbers photographed and recorded, and asset tags applied, make recovery possible if equipment does go. Insurers ask for this, and the time to do it is at commissioning.
The procedural layer
Most of this is not hardware.
Tell people the base exists. A sign on the enclosure with a contact number, stating what it is and that it must not be switched off, prevents a surprising proportion of incidents.
Include it in site inductions. Especially on multi-contractor sites where the survey team and the earthworks crews barely overlap.
Assign an owner. One named person responsible for the base station, known to the site team.
Put it in the handover. When a project changes phase or a contractor demobilises, the base station is exactly the kind of asset that falls through the gap.
Practical note on containers
A container-mounted base inherits the container’s security, which is usually good. It also inherits the container’s access list, which is usually longer than you’d like — everyone with a compound key can reach the base.
That’s the argument for the padlocked enclosure inside the locked container. Two layers, two different key holders, and the survey equipment isn’t accessible to everyone who needs the storage.
CTA: Our base station enclosures come with a padlockable full-height door and a stand drilled for floor or plinth fixing. Call 1300 769 359 to discuss your site.

Cable Entry and AnCable Entry and Antenna Lead-Throughs Explainedtenna Lead-Throughs: The Detail That Decides the Install

Every cable that enters an enclosure is a hole in that enclosure. That’s true whether it’s a base station box in a container or a machine control kit in an operator cab, and it’s the point where the two jobs share the same underlying discipline.
The failure mode is consistent and predictable. An oversized hole, a cable pushed through it, maybe some tape or silicone. Dust and water track in along the cable. The cable’s own weight, plus vibration, works the conductor at the terminal until it fatigues. Twelve to eighteen months later, an intermittent fault that nobody can find.
It’s a solved problem. It just has to actually be solved, on site, on the day.
Match the gland to the cable, not to the hole
A cable gland has a clamping range. The cable’s outside diameter has to sit inside that range, comfortably, not at either extreme.
Too large a gland doesn’t clamp the sheath. It looks tightened, it isn’t sealed, and it provides no strain relief.
Too small a gland either won’t accept the cable, or gets forced on and crushes the sheath, which damages the insulation and creates a stress point.
Check the cable’s actual outside diameter with callipers rather than trusting a catalogue figure, particularly on armoured or braided cable, and choose the gland accordingly. On a build with six or eight different cables, that means several different gland sizes, not one size drilled into a plate eight times.
Also match the gland material to the environment. Nylon glands are fine indoors and undercover. In UV exposure and high heat, metal glands last longer. Where there’s chemical exposure, check compatibility.
Antenna coax deserves a bulkhead, not a gland
GNSS antenna feeder and UHF radio feeder should enter through a bulkhead connector — typically N-type for the frequencies and cable sizes involved on a base station — rather than being passed through a gland as a continuous run.
Three reasons:
Serviceability. With a bulkhead lead-through, the external feeder can be disconnected and replaced without opening the enclosure or disturbing anything inside. With a continuous run through a gland, replacing a damaged feeder means a full rebuild of the internal termination.
Mechanical protection. The bulkhead takes any force applied to the external cable. Nothing is transmitted to the receiver’s connector, which is the fragile and expensive end.
RF integrity. A properly installed bulkhead maintains the coax’s characteristic impedance through the wall. A gland with the coax squashed in it does not, and the mismatch shows up as loss.
Pay attention to the internal jumper as well. Keep it short, keep the bend radius above the cable manufacturer’s minimum, and support it so it isn’t hanging off the receiver connector.
Strain relief is separate from sealing
This is the distinction people miss. A gland seals and provides some clamping. It is not a substitute for supporting the cable.
Every cable inside the enclosure should be clamped or cable-tied to a fixed point close to where it enters, so that the run from the clamp to the terminal is short, slack and carries no load. Every cable outside should be supported at intervals along its route, so the weight of a five-metre run isn’t hanging on the gland.
Where a cable crosses from a fixed structure to something that moves — a container door, a hinged panel, anything on a machine — it needs a service loop with enough slack for full travel, and flex-rated cable rather than fixed-installation cable.
Sealing is directional
Water tracks down, so entries want to be sealed against downward flow and ideally positioned so water doesn’t reach them in the first place.
Enter from below or the side where possible. A penetration in the top of an enclosure is a drain.
Use a drip loop. Take the cable below the entry point and back up. Water follows the cable to the bottom of the loop and drops off.
Seal from the outside. Sealant applied to the outer face of the penetration, so any water is stopped before it reaches the wall thickness.
On corrugated surfaces, penetrate the flat section, not the corrugation, and hood the entry.
The count of penetrations is the thing to design around
Here’s the point that gets missed on multi-system installs, and it matters far beyond base stations.
A single piece of equipment might need four cable entries. That’s manageable. But a machine carrying several separate systems — machine control, telematics, monitoring devices, a limiter, a camera system — can end up with five or six independent installations, each done by a different crew, at a different time, each drilling its own penetration.
Nobody owns the total. Each install is reasonable in isolation. Cumulatively, the cab or the enclosure ends up with a dozen holes of varying quality, and the ones done in a hurry are the ones that leak.
On a cab, that has a direct consequence: unsealed penetrations degrade cab pressurisation, which is the mechanism that keeps respirable dust out of the operator’s breathing zone. A cab with a good filtration system and six poorly sealed cable entries is not a pressurised cab.
The fix is planning the penetrations for all systems at once rather than one at a time — deciding entry points, gland sizes and routing before the first hole is drilled. That’s a coordination job more than a technical one, and it’s rarely anyone’s assigned responsibility.
What we build in
On base station enclosures, cable glands and antenna lead-throughs are available as an option, sized to the specific cables going in rather than a generic plate.
We also build braided harnesses and DC distribution in our own Brisbane workshop, which means the internal wiring in a fitted enclosure is assembled to a consistent standard, with terminations landed on DIN terminal blocks rather than made up on site.
If you tell us what’s going in and what’s coming out, we’ll drill and gland it before it ships. That’s considerably easier than doing it in a container in February.
CTA: Send us your cable schedule and we’ll size the entries. Call 1300 769 359 or email [email protected].

Solar Power for a Permanent GNSS Base Station

A base station that runs out of power at three in the morning and recovers by nine is worse than one that fails outright. The outright failure gets reported and fixed. The intermittent one gets blamed on the rovers, the radio, the weather and the operators for a fortnight before anyone checks the battery voltage log.
Undersized or poorly protected power is the most common cause of unreliable permanent base stations. It’s also the most straightforward to get right, because unlike antenna siting or radio propagation, it’s arithmetic.
Work out the load first
Everything follows from the continuous current draw. You need real numbers for:
The GNSS receiver. Check the manufacturer’s specification for continuous draw at your operating configuration, not the peak or the typical figure from a datasheet summary.
The radio, if fitted. This is usually the largest and most variable load, because transmit current is much higher than receive. A UHF base radio transmitting corrections continuously draws considerably more than the same radio idle. Use the transmit figure at your output power, not the average.
The modem, if fitted. Cellular modems draw more when signal is marginal and they’re working harder to hold a connection.
The cooling fan. Small, but it runs when it’s hot, which is also when the solar is producing — usually a wash.
Everything else. Router, switch, monitoring device, indicator lights.
Add them, convert to amp-hours per day, and that’s your daily energy budget. This is the number the whole system is sized from, and it’s the number most people guess.
Sizing the battery
Two constraints set the battery capacity: how many days of autonomy you want, and how deeply you’re prepared to discharge.
Autonomy. Three to five days is the usual target for a site base station in Australia. That covers a run of overcast days without intervention. Less than two days of autonomy means a wet week takes the base down.
Depth of discharge. This is where lithium iron phosphate and lead acid diverge sharply. A LiFePO4 battery tolerates deep discharge routinely. A lead acid battery discharged deeply and repeatedly loses capacity quickly. In practical terms, a lead acid bank has to be roughly twice the nominal capacity of a LiFePO4 bank to deliver the same usable energy over a comparable service life.
LiFePO4 costs more up front and is usually the better answer for a permanent installation, particularly where the enclosure is in a hot environment and the site doesn’t have anyone checking on it weekly.
Temperature matters. Battery capacity and charge acceptance both change with temperature, and a battery sitting in a hot container will behave differently from the datasheet. Charging LiFePO4 below freezing is a separate problem, relevant on high-altitude and southern sites in winter — most quality batteries with an integrated BMS handle this, but confirm it rather than assume it.
Sizing the solar array
Take the daily energy budget, divide by the worst-case daily solar yield for the site’s location and panel orientation, and add margin for panel soiling, temperature derating and controller losses.
The worst-case figure is the one that matters. Sizing to an annual average produces an array that works beautifully for nine months and fails through the shortest, cloudiest weeks of the year. Australian solar irradiation data by location is publicly available and worth using rather than estimating.
Practical points:
Fixed frames are fine. Tracking systems add moving parts and failure modes for a marginal gain at this scale.
Orientation and tilt. North-facing, at a tilt angle that favours winter yield rather than annual total, is the usual choice for a system sized around the worst month.
Shading is a cliff, not a slope. Partial shading of one panel can disproportionately reduce output from a string. Check the shading through a full day, in winter, when shadows are longest.
Soiling. Dust on a panel on a mine site is not a minor derate. Either accept a substantial soiling allowance in the sizing, or put panel cleaning on the maintenance schedule.
Mount them where they can be reached. Panels on a container roof that needs a scissor lift to access won’t get cleaned.
The charge controller
An MPPT controller extracts more from a given array than a PWM controller, particularly in cool bright conditions and when the array voltage is well above the battery voltage. For a permanent installation, MPPT is the default.
Two things to check when specifying:
Battery chemistry support. The controller must have a lithium charge profile if you’re running LiFePO4. A lead acid profile applied to a lithium bank charges it incorrectly.
Current rating with headroom. Size the controller above the array’s short-circuit current with margin, so it isn’t running at its limit on the best day of the year.
DC distribution and protection
This is the part that gets skipped, and it’s the part that causes fires and mystery faults.
A properly built base station DC system has:
A battery terminal fuse. Directly at the battery positive terminal, so a short anywhere downstream — including in the main cable — is protected. An MRBF or ANL type is standard.
A battery isolator switch. So the system can be shut down for work without pulling terminals.
Individual circuit protection. A breaker per circuit, so a fault in the modem doesn’t take down the receiver, and so faults can be isolated by someone who isn’t an electrician.
DIN rail and terminal blocks. Every connection landed on a terminal, not a twisted joint or a chocolate block. This is what makes a system diagnosable two years later by someone who didn’t build it.
A battery monitor or shunt. State of charge visible at a glance. Without it, nobody knows the system is marginal until it fails.
Correctly sized cable. Sized for the current and the run length, with voltage drop calculated rather than assumed. Heavy DC cable at low voltage is unforgiving of undersizing.
Proper terminations. Crimped lugs, heatshrink, and cable supported so the terminal isn’t carrying weight.
We build braided harnesses and DC distribution in our own workshop, so a fitted enclosure comes wired to a consistent standard rather than assembled on site with whatever was in the ute.
How this fits the enclosure
The base station enclosure has room inside for the receiver, radio, charge controller and DC distribution, with an internal backing panel and DIN rail available as an option. The battery mounts on the stand below the box, clear of the equipment.
For anything beyond a single standard battery — a larger bank, or a bank plus separate solar input protection — the mounting arrangement needs to be worked out before fabrication, because it affects the stand. Tell us the battery configuration when you enquire, not after the box arrives.
CTA: Talk to us about a base station enclosure with power and DC distribution built in. Call 1300 769 359 or email [email protected].

Ventilated vs Sealed Enclosures: An Honest Look at the Trade-Off

There’s a decision in every enclosure specification that people tend to make by accident. Ventilated or sealed. It gets decided by whichever quote came in first, or by an IP number copied out of an old specification, and the consequences show up two summers later.
The trade-off is simple to state and impossible to avoid: an enclosure that lets air move lets everything else in the air move too. You can have airflow or you can have ingress protection. Not both, at least not without spending significantly more.
What ventilated means in practice
A ventilated enclosure has deliberate openings — a mesh panel, louvres, a fan aperture — that allow air to exchange between inside and outside.
What you get:
Internal temperature stays close to ambient, rather than climbing above it
No thermal derating on the equipment inside
Much lower cost, because there’s no sealing system, no gaskets and no cooling hardware
Simpler maintenance — no gasket inspection, no desiccant, no condensation management
Lighter, because the enclosure isn’t doing thermal work through its walls
What you give up:
Dust gets in. On a mine site, quarry or unsealed haul road environment, it gets in continuously.
Moisture gets in. Not driving rain if the enclosure is undercover, but humidity, and condensation when the temperature swings.
Insects and vermin get in, unless the mesh is fine enough, and fine mesh restricts airflow.
The enclosure cannot be mounted in the open.
What sealed means in practice
A sealed enclosure has a continuous gasket, sealed penetrations and an IP rating that describes what it keeps out. IP66, for example, describes protection against dust ingress and against powerful water jets.
What you get:
Equipment stays clean and dry
Outdoor mounting becomes possible
Longer service intervals on the equipment inside
What you give up:
Heat has nowhere to go except through the enclosure walls. In direct sun, a sealed box becomes a solar oven.
To manage that, you need active thermal management — a heat exchanger, a thermoelectric cooler, or air conditioning. All of these cost money, consume power, and add their own failure points.
Or you oversize the enclosure substantially to increase surface area, which costs money and space.
Condensation becomes a management problem. A sealed box that breathes through a temperature cycle will accumulate water inside it unless it has a breather vent or desiccant.
The last point catches people out. A sealed enclosure isn’t a sealed environment. Air inside expands and contracts with temperature, and unless there’s a pressure equalisation path, the seal is being cycled. Add a breather and you’ve compromised the IP rating you paid for.
How to decide
The decision follows from where the enclosure is going, not from what’s in it.
Choose ventilated if: the enclosure will be installed undercover — inside a shipping container, shed, workshop, plant room, switchroom or covered compound area — and the ambient dust load is moderate. This covers the majority of permanent GNSS base station installations, because bases are usually established in a site compound.
Choose sealed if: the enclosure will be mounted in the open with no overhead protection, or the environment is severe enough that dust ingress will foul the equipment regardless. Coastal exposure, high-pressure wash-down areas, and dusty processing plant environments all point to sealed.
A middle path exists: a ventilated enclosure inside a purpose-built shelter or under a roof. This is often cheaper than a sealed cabinet with active cooling, and easier to service. Where the site can provide the cover, it’s usually the better engineering answer.
Where the Red Edge enclosure sits
We build a ventilated enclosure. It has an expanded aluminium mesh vent panel in the door and a cut-out for a cooling fan.
It is not IP-rated, and we don’t recommend exposed outdoor mounting without additional weather protection.
We say that plainly because the alternative is a customer discovering it after installation. The mesh door and the fan cut-out are there to move air, and that means dust and moisture can get in as well. The enclosure is built for undercover installation — containers, sheds, workshops, plant rooms.
If your site needs a sealed outdoor cabinet, that’s a different product, and there are Australian manufacturers who build them properly. We’d rather point you there than sell you the wrong box.
What to do about dust in a ventilated enclosure
If you’re going ventilated, a few things reduce the dust load without closing the box up:
Filter the fan intake. A filtered inlet with a serviceable element catches most of what a fan draws in. It needs to be on the service schedule, because a blocked filter is worse than no filter.
Positive pressure. A filtered fan blowing in, rather than out, keeps the enclosure slightly above ambient pressure, so leakage flows outward. This is the same principle used in operator cab pressurisation, and it works at enclosure scale.
Mount the vent away from the dust source. Vent panels facing away from a haul road or crusher see a fraction of the load.
Conformal coating. For equipment that’s going to live in a dusty environment for years, coated boards tolerate it better.
Schedule a blow-out. Compressed air through the enclosure at each service interval, with the equipment isolated. Ten minutes, once a quarter.
The specification mistake to avoid
Copying an IP rating from a previous specification without checking the thermal consequence is the most common enclosure error we see. IP66 gets written into a document because it appeared in the last one, the enclosure gets bought, it’s installed in a container in the Pilbara with no cooling, and the equipment inside starts throttling in November.
The right sequence is: establish where it’s going, establish the thermal load, then choose the ingress strategy that’s compatible with both. The IP rating is an output of that process, not an input.
CTA: Not sure which side of this decision your site sits on? Call 1300 769 359 and talk it through with us before you specify.

Container-Mounted GNSS Base Stations: A Practical Setup GuideAlmost every Australian site of any size has a shipping container in the compound. It’s already there, it’s already lockable, it’s usually already near power, and it’s shaded. For a permanent GNSS base station, that combination is hard to beat — which is why container-mounted bases have become the default on mine sites, civil projects and renewables construction.Doing it well takes a bit more than putting the receiver on a shelf.Why a container worksIt’s undercover. A ventilated enclosure needs to be out of direct weather, and a container provides that without any additional structure.It’s secure. The container is already locked at night and already part of the site’s security arrangements. A base station inside it inherits that.It’s stable. A container sitting on its corner castings or a prepared pad doesn’t move. That matters, because a base station’s whole job is to sit on a known coordinate.It has power, usually. Compound containers are often already connected to a genset, mains or a solar array, which removes the biggest constraint on a permanent base.It’s shaded. Not cool — a closed container in summer gets hot — but out of direct sun on the equipment itself.Heat is still the main problemA steel box in the sun is a good oven. Container internal temperatures well above ambient are routine through a Queensland or Pilbara summer, and that’s before you add a transmitting radio.So the container solves the weather problem and makes the heat problem worse. Three things help:Ventilate the container itself. Whirlybirds, louvres, or a powered extraction fan. If the container has no air movement at all, nothing you do to the enclosure inside it will be enough.Ventilate the enclosure. A mesh vent panel and a fan cut-out let the enclosure exchange air with the container. A thermostat-controlled fan runs only when it needs to, which matters if the base is on battery and solar.Position sensibly. Away from the sun-facing wall, away from the roof, and not directly above a genset or compressor.Antenna siting is the hard partThe container is the easy bit. The antenna is where container installs get compromised, because the antenna needs a clear view of the sky and the container is a metal box.Practical guidance:Roof mount is the usual answer. A pole or mast on the container roof, braced properly, gets the antenna above the container and clear of surrounding structures.Watch the multipath. A container roof is a large flat conductive surface. An antenna mounted close to it will see reflected signals. Getting the antenna up on a mast rather than sitting it on the roof deck makes a measurable difference.Keep the coax run short and protected. Every metre of feeder is loss, and every unsupported metre is a future failure. Run it in conduit or tray, support it at intervals, and bring it into the enclosure through a bulkhead lead-through rather than a gland.Think about the whole compound. Cranes, light towers, laydown stacks and other containers all move over the life of a project. An antenna position that’s clear on day one can be shadowed by month six.The base coordinate is the thing that has to survive. If the container is ever moved, relevelled or replaced, the antenna position changes and the base is no longer where it thinks it is. Fix the container’s position in the site plan and make sure the site team knows the container can’t be shifted without the survey team being told.Cable entry into the containerContainer walls are corrugated steel, which makes for awkward penetrations. A few conventions that work:Use the existing vent apertures or a purpose-cut and glanded penetration in a flat section, not the corrugation.Seal from the outside, with a hood or drip loop above the entry, so water running down the corrugation doesn’t track in.Bring antenna coax and power in at different points where practical, to keep the DC run away from the feeder.Label everything at both ends. Containers get re-fitted, and unlabelled cable gets cut.Mounting the enclosure insideThe base station enclosure and stand together stand about 1,850 mm. In a standard container that leaves clearance above, and puts the equipment at a workable height.The stand feet are drilled for floor or plinth fixing. Bolting the stand to the container floor is worth doing even where it feels unnecessary — a container gets moved, tilted on a tilt-tray, and shunted, and an unfixed 1.8 m assembly with a battery on it will go over.Where floor space is scarce, the wall-mount version without the stand fixes to the container wall directly, with the battery relocated to a separate mount.Leave working space in front of the door. A full-height hinged door needs room to swing, and someone will eventually need to get in there with both hands and a multimeter.Power and batteryIf the compound has a supply, the base runs off it with a battery for ride-through during genset changeovers and outages. If it doesn’t, solar and a deep cycle battery are the standard answer.Either way, the DC side wants a proper isolator, protection on each circuit, and a battery monitor so the state of charge is visible without a meter. We cover this in more detail in a separate article on powering a permanent base station.The battery mount on the stand puts the battery below the enclosure, clear of the equipment, which keeps the heaviest item low and makes swaps straightforward.Security and accessThe container gives you perimeter security. The enclosure’s full-height door has a hasp for padlocking, which gives you a second layer — useful where a lot of people have container access but only a few should be inside the base station.Padlocking also stops the well-meaning intervention: someone opening the box because a light is flashing, and turning something off.Getting the sizing right before you orderThe most common problem we see is an enclosure sized to the receiver and nothing else. By the time the radio, the charge controller, a modem, the DC distribution and a spare gland run are in there, the box is full and there’s nowhere to put the thing that gets added next year.Before ordering, list every item going inside, with dimensions, and add space for one more. We build to order in Brisbane, so a non-standard size is a normal request rather than a special.CTA: Tell us what needs to fit inside and we’ll size the enclosure to suit. Call 1300 769 359 or email [email protected].

GNSS Base Station Enclosures: What a Fixed Base Actually Needs

A permanent GNSS base station is a small collection of expensive, sensitive equipment that has to sit in one place, powered and communicating, for months or years at a time. The receiver, the radio or modem, the charge controller, the DC distribution and the battery all need somewhere to live. On a lot of sites, that somewhere ends up being a plastic tub in the corner of a container, a milk crate, or a hastily drilled sheet of ply screwed to a wall.
That works until it doesn’t. The failures are rarely dramatic. A fan-less box in a north-facing container gets hot enough through summer that the receiver starts dropping out in the afternoon. A power lead gets snagged and pulls a terminal off. Someone borrows the battery for a light plant. An antenna cable gets kinked behind a shelf. Each one costs a rover crew or a machine control fleet a session of positioning, and the cause is almost never obvious from the field end — the crew just sees corrections stop.
The enclosure is the part of a base station install that gets the least thought and prevents the most of these problems. This guide covers what to look for.
What lives inside a base station enclosure
A typical fixed base has more in it than people expect:
The GNSS receiver. On a permanent install this is usually a dedicated base receiver rather than a rover doing double duty. It needs to stay powered, stay cool and stay put.
A radio or modem. Either a UHF radio broadcasting corrections locally, a cellular modem pushing to a caster, or both. Both generate heat under transmit.
A charge controller. If the base runs on solar or an unreliable site supply, there’s an MPPT or PWM controller between the source and the battery.
DC distribution and protection. Breakers or fuses, an isolator, terminal blocks, and ideally a shunt so someone can see the state of charge without pulling covers off.
A battery. Usually 12 V, and usually the heaviest single item, which is why it belongs low and separate rather than sitting on a shelf above the electronics.
Fitting all of that into a box designed for something else is where most improvised installs come unstuck. There’s either no room for the DC gear, or no way to get the antenna cables in without leaving a hole.
Heat is the first constraint
Electronics in a sealed metal box in the Australian sun will cook. A GNSS receiver and a transmitting radio together produce a steady thermal load, and an unventilated enclosure has nowhere to put it except through the walls. Internal temperatures well above ambient are normal in that situation, and the practical result is thermal throttling, shortened battery life and intermittent dropouts that look like a signal problem rather than a heat problem.
There are two ways to deal with it. Move air through the box, or seal the box and move heat out of it some other way — a heat exchanger, a thermoelectric cooler, or simply a much bigger enclosure with a lot more surface area.
Moving air is far cheaper and far simpler. A vented door and a fan cut-out handle the thermal problem for a fraction of the cost of a sealed, actively cooled cabinet. The trade-off is direct and unavoidable: air that carries heat out also carries dust and moisture in. This is not a detail to gloss over, and we’ve written about it separately, because it determines where the enclosure can and can’t go.
Ventilated enclosures are for undercover installation
The Red Edge base station enclosure is a ventilated design. The door carries an expanded aluminium mesh vent panel, and there’s a cut-out for a cooling fan. It is not IP-rated, and we don’t recommend exposed outdoor mounting without additional weather protection.
That’s a real constraint, not a caveat. It means the enclosure is built for:
Shipping containers and site offices
Sheds and workshops
Plant rooms and switchrooms
Covered areas within a site compound
And not for a bare post in the open on a greenfield site. If the base has to sit fully exposed, you need a sealed, IP-rated cabinet with a thermal management strategy that isn’t ambient airflow, and that is a different and more expensive product. Knowing which of those two situations you’re in before you order is the single most useful decision in the process.
Construction: why the material and the welding matter
The enclosure is 3 mm aluminium, TIG welded throughout, in a natural aluminium finish. A few practical consequences follow from that.
Aluminium doesn’t rust, which matters on coastal sites and in wash-down areas. It’s light enough that a two-person lift is realistic during install, which is not true of an equivalent steel cabinet. And 3 mm is thick enough that the box holds its shape when it’s dragged across a container floor, bumped by a forklift tyne, or drilled for a new gland run two years after it was built.
TIG welding throughout, rather than folding and riveting, means the seams don’t work loose under vibration. Containers and plant rooms both vibrate — from doors, from machinery, from vehicles moving nearby — and a riveted box slowly rattles itself into a looser box.
The finish is left as natural aluminium as standard, and can be powder coated or painted to a site colour where a client’s standards require it.
The stand and the battery
The box sits on a matching stand, 950 mm high, painted black, with a braced welded frame. The stand carries an integrated 12 V battery mount, 500 × 190 × 45 mm, positioned below the box so the battery sits clear of the equipment.
That arrangement solves a few things at once. It keeps the heaviest item at floor level, which makes the whole assembly stable. It keeps battery gassing and any leakage away from the electronics. It puts the receiver and radio at roughly chest height, which is where you want them when you’re commissioning a base at 5 am with a head torch. And it lets someone swap a battery without opening the equipment compartment at all.
Overall height with the box mounted is approximately 1,850 mm. The stand feet are drilled for floor or plinth fixing, so the assembly can be bolted down in a container or to a concrete plinth in a compound.
There’s also a wall-mount version without the stand, for plant rooms where floor space is the constraint and there’s a suitable structural wall.
Cable entry is where installs are won or lost
Every cable that enters the enclosure is a hole in it. Antenna feeder, power in, ethernet or serial out, solar input — that’s four to six penetrations on a typical base.
Done properly, each one gets a gland or a bulkhead connector sized to the cable, tightened onto the sheath, with the cable supported so the weight and any movement is taken by a clamp rather than by the gland or the terminal. Antenna coax gets an N-type bulkhead lead-through rather than being passed through a gland, so the connector is serviceable from outside and the run inside is short and fixed.
Done badly, cables come in through an oversized hole with a bit of tape around them, and the enclosure becomes a funnel for dust and water and a strain relief for nothing.
We build cable glands and antenna lead-throughs in as an option, sized to what’s actually going in, along with braided harness and DC distribution assembled in our own workshop.
Built to order, and what “standard supply” means
The standard supply is the box and the stand, built to order and empty. The receiver, radio, charge controller, battery, fan and internal wiring shown in the product photographs are an example of a customer fit-out — they are not part of the standard supply.
This matters for procurement. If you want a wired and tested unit delivered ready to power up, that’s a fitted unit and we quote it as a separate line, with the internal scope agreed before fabrication starts. If your own electrical team is doing the fit-out, the empty box with a backing panel and DIN rail is usually the right buy.
Options on the standard box include powder coat or paint to your colour, a cooling fan fitted with or without a thermostat, an internal backing panel and DIN rail, cable glands and antenna lead-throughs, the wall-mount variant, and non-standard sizes to suit equipment that doesn’t fit the standard envelope.
Where the enclosure sits in the wider base station decision
An enclosure is one part of a permanent base install. The others — antenna siting and sky view, mount stability, the coordinate the base is set on, radio range and licensing, and how corrections get to the rovers or machines — are covered in our permanent GNSS base setup guide, and the underlying positioning concepts in our explainer on how RTK works.
It’s worth being clear about sequence. Decide the site and the correction path first, because those determine whether you need a local radio base at all. Then size the enclosure to the equipment that decision leaves you with. Ordering the box first and finding the radio doesn’t fit is a common and avoidable annoyance.
Talk to us about what needs to fit
We fabricate these in our own Brisbane workshop, which means non-standard sizes and one-off configurations are normal work rather than a special request. Tell us what needs to go inside — receiver, radio or modem, charge controller, battery, and any site-specific gear — and we’ll size it.
CTA: Call 1300 769 359 or email [email protected] to discuss a base station enclosure for your site. Built to order in Brisbane, freighted Australia-wide.

Installing a Stonex Machine Control System

The question that gets asked first
Every plant manager asks the same thing: how long is my machine off the job?
Stonex’s own guidance is that a quick demonstration installation typically takes two to four hours, while a full professional setup may require up to a working day — six to eight hours. \[MFR]
\[VERIFY] — confirm this against Red Edge’s actual experience on Australian machines. Manufacturer figures are usually derived under favourable conditions on common machine types; a real figure from your technicians, stated honestly, is more useful and more credible than a manufacturer optimum.
Either way, plan it into a period when the machine is not on the critical path. Downtime costed at your plant rate is a genuine line item that never appears on a quote.
What gets fitted
Angle sensors on the machine geometry — boom (single or dual), stick, bucket and frame for an excavator; on the blade for a dozer.
GNSS antennas, where the configuration includes them. Cab roof for excavators; for wheel loaders, either the rear frame or the front frame depending on machine design.
The receiver, where fitted.
The display and its mount.
Connection box, cabling and looms.
What separates a good install
The hardware is the same regardless of who fits it. Installation quality is what determines whether the system is still working in two years.
Sensor mounting. Earthmoving machines destroy poorly mounted equipment. Mounts need to be secure, correctly positioned and protected from strikes. A sensor that shifts on its mount produces errors that are difficult to diagnose, because nothing has obviously failed.
Cable routing. Cables need to be routed away from pinch points, heat, and anywhere they will chafe against moving components. Poor routing is the single most common cause of intermittent faults, and intermittent faults are the most expensive kind to chase.
Connector protection. Connectors are where dust and moisture get in. Sealing and positioning matter.
Display position. Visible at a glance without competing with the operator’s view of the work. This is a decision made at fit-out and lived with for years — worth getting right rather than accepting wherever the bracket happened to fit.
Antenna geometry. Where two antennas provide heading, the separation between them affects precision. Follow the specified geometry rather than mounting them where it is convenient.
Machine compatibility
Stonex states installation across a wide range of excavator brands, models and sizes. \[MFR]
Worth confirming specifically for your machines rather than relying on the general statement — particularly for older machines, unusual configurations, or anything with non-standard boom arrangements. Articulated and two-piece booms in particular are a question worth asking directly.
Warranty
Confirm with your machine manufacturer or dealer what aftermarket fitment means for your specific machine and warranty position. This varies by manufacturer and it is worth getting in writing rather than assuming in either direction.
Downtime planning
Schedule around work. Fit during planned maintenance, between jobs, or in a lull.
Don’t do the whole fleet at once. Something will not go smoothly, and you want capacity elsewhere when it does.
Allow for commissioning. Installation is not the end. Configuration, calibration and verification follow, and they take time.
Train close to use. Training delivered weeks before the machine goes into guided production is training that has to be repeated.
Who does it
Red Edge provides Stonex installation, calibration, operator training and technical support.
\[VERIFY] — Red Edge’s live dozer page describes certified technicians using fully-equipped mobile service vehicles throughout Australia. If that is accurate and substantiable, it is a strong point worth making consistently across the site. Confirm before repeating it. Coverage claims are the ones a competitor complaint targets first.
CTA: Talk to Red Edge Resources about installation scheduling and realistic downtime for your machines.