Site Calibration for Stonex Systems

What it does
GNSS gives position in a global reference frame. Your design is drawn in a local site coordinate system. Site calibration is the mathematical relationship between the two.
Without it, the machine knows where it is on the planet and not where it is on the job.
Why it is the highest-consequence step
Most errors in machine control announce themselves. A failed sensor stops reporting. A lost correction shows a degraded solution status. The operator sees something is wrong.
A bad calibration does none of that. The system reports full accuracy, the operator sees a normal display, and the machine produces precise, consistent, confidently wrong work at full production rate.
Nobody finds out until conformance survey, by which point the work is done.
What a good calibration requires
Adequate control points. Enough, and well distributed across the work area — horizontally and vertically. A calibration computed from points clustered in one corner will not hold at the other end.
Good control. The calibration inherits the quality of the control it is computed from. Poor control produces a poor calibration that looks fine.
Coverage of the work area. Reliable within the area bounded by the control. Extrapolating beyond it is where errors grow silently.
Vertical control specifically. Vertical is where GNSS is weakest and where earthworks tolerance is tightest. Do not treat vertical control as an afterthought.
Residuals examined, not glanced at. The residuals tell you how well the calibration fits. Consistently large residuals in one area indicate a problem with the control or the site coordinate system — and both are worth resolving before machines start, not after.
The verification step
A calibration is not complete until it has been checked against control that was not used to compute it.
Calibration computed and applied
Rover or machine taken to an independent known point
Position compared
Within tolerance, and recorded
Repeat at points spread across the site, including the extremities
That last part matters. A calibration can be excellent in the middle and poor at the edges. Check where the work will actually happen.
Failure modes
Multiple calibration files. The most common and most expensive. Different files circulating, an old one still on one machine, a subcontractor on their own. Every machine internally consistent, all disagreeing.
Undocumented recalculation. Someone re-runs the calibration to fix a problem and does not tell anyone.
Knocked control. A control point disturbed after calibration. Everything referencing it inherits the error.
Extrapolation. Work extends beyond the calibrated area and nobody re-establishes control.
No routine verification. Drift found by conformance survey rather than by daily checking.
Making it stick
Single source of truth. One file, one owner, one distribution point, version-controlled and dated.
Daily known-point check. Part of the pre-start routine, with a defined tolerance, a recorded result and a stated action on failure.
Change control. Recalibration is a notified, documented event with confirmed rollout before work resumes.
Protect the control. Control points get hit on active sites. Physically protect them and check them periodically.
Include everyone. Subcontractors on the site datum, contractually if necessary.
The link back to why you bought it
Machine control reduces on-foot exposure because people stop making manual grade checks. They stop only when they trust the system. They trust it only when the calibration is right and verified.
A site with a shaky calibration either keeps checking manually — retaining all the exposure while paying for the technology — or stops checking and builds errors. Neither is what you paid for.
Red Edge provides installation, calibration, operator training and technical support for Stonex systems. Site calibration in particular is worth having done properly by someone competent, and worth having the verification documented.
CTA: Red Edge Resources provides site calibration as part of Stonex installation and commissioning.

Preparing Design Files for STX-MC

The uncomfortable truth about 3D
Without guidance, an experienced operator provides a sanity check. Something looks wrong, they stop and ask.
With 3D guidance, the operator is working to the screen. If the model is wrong, the model gets built — accurately, efficiently, and at full production rate. The machine is not going to query it.
That shifts responsibility upstream. Model quality is now a production risk, not a drafting detail.
What the software accepts
STX-MC supports importing georeferenced projects, with DXF specifically referenced in Stonex material, and design file management supporting multiple CAD formats.
\[VERIFY] — obtain and publish the current supported format list. This is the single most-asked practical question from technical buyers, and a specific answer is genuinely useful content. A vague answer looks evasive.
From drawing to model
A design drawing and a machine-ready model are different things.
A drawing communicates intent to a human who will interpret it. A model is a defined surface a machine can query at any position. Producing the second from the first requires:
Surface definition. A continuous surface, not a collection of lines and levels. Gaps produce areas where the machine has no design to work to.
Correct georeferencing. Positioned correctly in the site coordinate system. A model that is right in shape and wrong in position is worse than no model.
Appropriate detail. Enough to define the surface accurately, not so much that the file is unwieldy.
Clean geometry. Duplicate surfaces, crossing triangles and zero-area faces cause unpredictable behaviour.
Common problems
Wrong coordinate system. The model is in one system, the site is calibrated to another. Everything is consistently offset. Catch it with a known-point check before work starts.
Units. Metres versus millimetres, or an imported file in feet. Usually obvious immediately, occasionally not.
Vertical datum confusion. Horizontal correct, vertical referenced to something different. More insidious, because it can look plausible.
Incomplete surfaces. Holes in the model where the machine has no guidance.
Superseded revisions. The model is correct but out of date.
Design errors. The model faithfully represents a design that is itself wrong. Machine control will build it exactly.
Verification before release
Before any model goes to a machine:
Check against known points. Query the model at surveyed control locations and compare. Catches coordinate system and datum errors immediately.
Visually inspect the surface. Look for holes, spikes, and areas that do not look like the design intent.
Sanity-check key levels. Pick critical points — inverts, finished levels, tie-ins — and confirm against the drawing.
Confirm the revision matches the current issued design.
Record the verification. Who checked, when, against what.
This takes under an hour on a typical model and it prevents the most expensive category of failure in 3D machine control.
Revision management
One authoritative location for current models
Clear, visible revision identification on the machine
Defined process for distributing updates
Confirmation each machine is current before work resumes on a revised area
Record of which revision was used where
Who should do this
Someone with both CAD competence and an understanding of survey and site coordinate systems. That combination is not universal — a good CAD operator without survey understanding will produce a well-formed model in the wrong place.
If nobody in your operation has both, the options are to train someone, use a consultant, or have the designer supply machine-ready models as a deliverable. The last is worth pursuing contractually on projects where it is achievable.
CTA: Red Edge Resources can advise on data preparation and workflow for STX-MC.
Pre-publish flags: \[VERIFY] supported format list — high value, get a specific answer.

The 3D Pro Data Workflow Explained

The framing that helps
Stonex splits 3D Pro work into two phases, and it is a genuinely useful way to think about it:
OFF-MACHINE — everything done in the office and in the field to generate and georeference the project.
ON-MACHINE — using that project to excavate.
The distinction matters because contractors buy the on-machine part and frequently do not plan for the off-machine part. That is the most common reason a 3D system underdelivers.
Unlike 1D and 2D, where an operator can set up what they need in the cab, a 3D Pro project requires several steps before a machine starts.
The OFF-MACHINE phase

  1. Obtain the design. From the designer, engineer or client. In a format that can be worked with — which is not guaranteed, and is worth establishing contractually at the start of a project rather than discovering at the start of earthworks.
  2. Convert to a usable model. Design drawings and machine-ready models are not the same thing. Producing a surface the machine can work to is real work with real skill attached.
  3. Georeference it. The model must sit correctly in the site coordinate system. Stonex supports importing georeferenced projects including DXF. \[VERIFY] — confirm the full current supported format list.
  4. Establish site control. Control points, surveyed to an appropriate standard, distributed across the work area.
  5. Calibrate the site. Tie GNSS positioning to the site coordinate system so machines and rovers work on a consistent datum.
  6. Verify. Check the calibration against independent known points before releasing anything to machines.
  7. Distribute. Get the correct, current model to every machine that needs it.
    The ON-MACHINE phase
    By comparison, straightforward: load the project, verify against a known point, work to the design, with real-time cut and fill displayed.
    That asymmetry is the point. Most of the work happens before the machine starts.
    Who owns it
    The question that decides whether 3D succeeds.
    On a large project, a dedicated engineer or surveyor. On a mid-sized contractor, usually a portion of an existing engineer’s or surveyor’s week — and it needs to be an acknowledged portion, not an assumption.
    What does not work: leaving it to whoever is free, or expecting the operator to sort it out. The operator’s job is on-machine.
    Version control
    The failure mode that costs the most:
    Design revisions happen. If machine 1 is on revision C and machine 2 is on revision D, both are working confidently and one is wrong. Nobody finds out until conformance.
    Minimum discipline:
    One authoritative source for current models
    Clear revision identification, visible on the machine
    A defined process for pushing updates to every machine
    Confirmation that each machine has the current version before work on a revised area
    A record of which revision was used where, for as-built purposes
    The cost nobody quotes
    Data management does not appear on a hardware quote and it is a genuine ongoing cost: the time to prepare models, the software to do it, the person’s hours, and the training to do it competently.
    Budget it explicitly. A 3D system with no data management resource is a 3D system that will be run in 2D mode within a few months.
    The test before you buy
    Ask yourself three questions:
    Can I reliably get design data in a usable format on my projects?
    Do I have someone who can prepare and georeference models, or can I train them?
    Have I allowed time for this in my project resourcing?
    Three yeses and 3D Pro will deliver. Any no needs resolving first — and it is cheaper to resolve it before the purchase than after.